IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO. 3382 OF 2017 IN FIRST APPEAL (ST.) NO. 11887 OF 2017 The Manager, The New India Assurance Co. Ltd.

....Applicant V/s.

Shabana Samir Shaikh & Ors.

....Respondents Mr. Sudhakar Pandaram I/b. Milind V. More for the applicant in CAF 3382/2017, CAF 3383/2017 and in FAST 11887/2017 and for R.No.1 in CAFST 8212/2018.

Mr. S.G. Thorat for R.Nos.1, 2, 4 and 5 and for applicant in CAFST 8212/2018.

CORAM: SMT. ANUJA PRABHUDESSAI, J.

DATED : 01st MARCH, 2019.

P.C.:

.

Mr. Sudhakar Pandaram, learned counsel for the applicant submits that the appellant has not raised any statutory defence. He prays that the notice to respondent no.6 be dispensed with. In the light of above statement, notice to respondent no.6 is dispensed with. 2.

By this application, the applicant has sought to condone the delay of 55 days in filing the appeal.

3.

Having considered the reasons stated in paragraph 3 of the application, which in my considered view, constitute sufficient ground, delay is condoned. Appeal be registered after removal of office objections, if any.

4.

Civil Application stands disposed of accordingly. (SMT. ANUJA PRABHUDESSAI, J.) 1/1