M/S. Sesa Sterlite Limited v. State Of Maharashtra, Through Ministry Of Industries And ORS
ppn 1 502.wp-7716.14.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION PRACHI PRANESH NANDIWADEKAR Date: 2024.03.06 12:47:50 +0530 PRACHI PRANESH NANDIWADEKAR WRIT PETITION NO.7716 OF 2014 M/s.Sesa Sterlite Limited .. Petitioner
Versus
State of Maharashtra, through Ministry of Industries & Ors.
.. Respondents --- Mr.Harsh Sheth i/by MDP & Partners for the petitioner. Ms.Shyamali Gadre (through VC) i/by Little & Company for the respondent no.2-MIDC.
Mr.N.C. Walimbe, Addl.G.P. a/w Mr.A.P. Deolekar, AGP for respondent. ---- CORAM : A.S. CHANDURKAR & JITENDRA JAIN, JJ.
DATE : 5th March 2024 P.C.:- .
Not on board. Taken up on the production board. 2.
In paragraphs 3 and 8 of the judgment dated 9th February 2024, the expression "889.579 acres" shall be replaced by the expression "513.97 acres." Similarly, the expression "395.368 acres" shall be replaced by the expression"37 acres."
3.
Corrections be carried out in the original judgment and the corrected judgment be uploaded.
4.
The learned counsel for the petitioner seeks extension of continuation of the interim order by submitting that the steps have been
ppn 2 502.wp-7716.14.doc taken to challenge the aforesaid judgment before the Supreme Court. He prays for extension by period of two weeks. This request is opposed by learned counsel for respondent no.2 on the ground that this request has not been referred to in the praecipe. She further submits that since time of four weeks was already granted, this request may not be accepted. 5.
Considering the fact that corrections have been made in paragraphs 3 and 8 of the judgment dated 9th February 2024, the interim order shall continue to operate for further period of two weeks in addition to the period for which it was to operate as per the judgment dated 9th February 2024.
JITENDRA JAIN, J.
A.S. CHANDURKAR, J.