Savitra Ramchandra Jadhav And ANR. v. The Maharashtra State Road Transport Corporation Through Its Divisional Manager
10-ia-3481-2021.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION INTERIM APPLICATION NO.3481 OF 2021 IN FIRST APPEAL (ST.) NO.30412 OF 2019 VISHAL SUBHASH PAREKAR Savitra Ramchandra Jadhav ...Applicant vs.
The Maharashtra State Road Transport Corp.
...Respondent
VISHAL SUBHASH PAREKAR Date: 2021.11.24 14:49:03 +0530 Mr. Pritesh Bohade, for the Applicant.
Ms. Ayodhya Patki i/b. Mr. Nitesh Bhutekar, for the Respondent. CORAM :
N. J. JAMADAR, J.
DATE :
NOVEMBER 24, 2021 P.C.:
.
Heard the learned counsel for the applicant and respondent No. 1.
2.
It appears that the applicant/claimant has not yet withdrawn 50% amount of compensation along with interest accrued thereon which was ordered to be paid by an order dated 3rd March, 2020, while granting stay to the execution, operation and implementation to the impugned award.
3.
In the circumstances, at present there is no justifcation to entertain the application.
4.
The application thus stands disposed of with liberty to the Vishal Parekar, P.A.
...1
10-ia-3481-2021.doc applicant to seek further withdrawal, in case of necessity, after the withdrawal of the said amount in terms of the order dated 3rd March, 2020.
(N. J. JAMADAR, J.) Vishal Parekar, P.A.
...2