Executive Engineer Maharashtra State Electiricity Distribution Co.Ltd. v. Shri.Sayaji Dyanoba Yadav And ANR.
ppn 1 40.caf-3820.13.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO.3820 OF 2015 IN FIRST APPEAL (ST.) NO.29625 OF 2015 ALONG WITH FIRST APPEAL (ST.) NO.29625 OF 2015 Executive Engineer, Maharashtra State Electricity Distribution Co. Ltd.
..
Applicant Vs.
Sayaji Dyanoba Yadav & Ors.
..
Respondents --- Mr.Kiran Gandhi i/by M/s.Little & Co. for the applicant. Ms.Shraddha Pawar i/by Mr.Dilip Bodake for the respondent nos.1 & 2. Mr.Kedar Jaysing Patil for the respondent no.3. --- CORAM : R.D.DHANUKA, J.
DATE : 4th November 2019 P.C.:
.
By this civil application, the applicant seeks condonation of delay of 253 days in filing the appeal. The applicant has explained the delay in paragraphs 3 to 5 of the civil application. Objections to this civil application are mentioned in the affidavit-in-reply filed by the respondent nos.1 & 2. There are hardly any objections in the civil application.
2.
In my view, the civil application is sufficiently explained. The explanation for condonation of delay is accepted. The applicant has already deposited the entire decreetal amount before the trial Court. Civil application is made absolute in terms of prayer clause (a). No order as to costs.
ppn 2 40.caf-3820.13.doc 3.
Place the first appeal on board for 'Admission' after all the objections are removed on 2nd December 2019. R.D.DHANUKA, J.