IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO. 5 OF 2019 IN REVIEW PETITION (ST) NO. 33633 OF 2018 Pradnya Pramod Latkar ..... Applicant

VERSUS

Mangesh Vitthal Wadekar & Anr.

..... Respondents Mr.Samarth Moray, i/b. Mr.V.S.Talkute for the Applicant/Petitioner. None for the Respondents.

CORAM :

R.D. DHANUKA, J.

DATE :

3rd MARCH, 2020 P.C.

There is delay of delay of 9 days in filing review petition. Heard Mr.Moray, learned counsel for the applicant and have perused the averments made in the civil application. Delay is explained in paragraph (2) of the civil application. Civil application is accordingly made absolute in terms of prayer clause (a). No order as to costs. [R.D.DHANUKA, J.]