IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED: 11.12.2023

CORAM:

THE HONOURABLE MR. JUSTICE G.K.ILANTHIRAIYAN A.S.Nos. 1284 of 2003, 1094 of 2004 & 134 of 2005 A.S.No. 1284 of 2003 The Superintending Engineer, Mettur Dam.

....

Appellant Vs

1. Pachamuthu 2.The Land Acquisition Officer, ....

aside the Judgment and Decree dated 29.02.1996 in LAOP.No.10 of 1994, A.S.No. 1094 of 2004 The Superintending Engineer, Mettur Thermal Power Station, Mettur Dam.

....

Appellant Vs

1. Poosari

2. Munusi

3. Ramasamy

4. Marimuthu

5. Arumugam

6. Minor Malarkodi (by mother and natural guardian Munisi, 2nd respondent herein) 7.The Land Acquisition Officer, ....

aside the Judgment and Decree dated 29.02.1996 in LAOP.No.11 of 1994, A.S.No. 134 of 2005 The Superintending Engineer, Mettur Dam.

....

Appellant Vs

1. Iyyavu

2. Sengodan

3. Periysamy (died) 4.The Land Acquisition Officer, 4.Nangammal 5.Raji

7.Thangavel 8.Rajendran 9.Easwari [R5 to R9 are brought on record as LRs of the deceased 3rd respondent as per order datd 31.12.2002 made in CMP.Nos.4663 to 4665/2002 by NBVJ & SKKJ) .... aside the Judgment and Decree dated 29.02.1996 in LAOP.No.35 of 1992, In all Appeal Suits For Appellant : Mrs.Hemalatha Gajapathy For Respondents : No appearance COMMON JUDGMENT These Appeal Suits have been filed as against the Judgment and Decree dated 29.02.1996 passed in LAOP Nos. 35 of 1992 and 10 & 11 of 1994 by the Subordinate Judge, Salem, thereby enhancing the compensation in the award passed by the Land Acquisition Officer.

2. The learned counsel appearing for the appellant would submit that the enhanced compensation amount has already been deposited before the Trial Court with accrued interest.

3. This Court also seen that there is no infirmity or illegality in the award passed by the Trial Court by enhancing the compensation. That apart, the entire enhanced compensation have been now withdrawn by the respondent.

4. Recording the said submission, all the Appeal Suits are closed. No costs.

11.12.2023 Internet:Yes Index:Yes/No Speaking/Non speaking order Lpp To

1. The Sub Court, Salem.

2.The Land Acquisition Officer,

3. The Section Officer, V.R.Section, High Court, Madras

G.K.ILANTHIRAIYAN. J, Lpp A.S.Nos. 1284 of 2003, 1094 of 2004 & 134 of 2005 11.12.2023