East Coast Constructions And Industries Ltd v. The Project Director
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 31.07.2020
CORAM:
THE HONOURABLE MR.JUSTICE N.SATHISH KUMAR A.No.537 of 2019 M/s.East Coast Constructions & Industries Ltd., Buhari Buildings, No.4, Moores Road, Chennai-600 006 rep. By its Director, Mr.S.A.Mohamed Mohideen . . . Applicant
Versus
The Project Director, Kolkata Municipal Corporation, Kolkata Environmental Improvement Project, 2nd Floor, Business Towers, 206, AJC Bose Road, Kolkata -700 017 . . . Respondent PRAYER: Application filed under Order XIV Rule 8 of original side rules r/w. SEC 9(ii)(b) of the Arbitration and Conciliation Act, 1996, to extend the time for completion of arbitral proceedings and passing of award by the Arbitral Tribunal, for a further period of 10 months i.e., until 31.07.2019. For Applicant : Mr.Vishnu Mohan For Respondent : No Appearance http://www.judis.nic.in
N.SATHISH KUMAR, J.
dn
ORDER
Today, when the matter is taken up for hearing, the learned counsel for the applicant submitted that award was already passed by the Arbitral Tribunal in the matter. In such view of the matter, this Court finds that nothing survives for adjudication in this application. Accordingly, this application is dismissed as having become infructuous. 31.07.2020 dn Index : Yes/No Internet : Yes/No Speaking/Non Speaking A.No.537 of 2019 http://www.judis.nic.in