R.Prabakar v. The Asst Executive Engineer,
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 17.07.2023
CORAM:
THE HONOURABLE MR.JUSTICE D.KRISHNAKUMAR AND THE HONOURABLE MR.JUSTICE P.B. BALAJI R.Prabakar ...
Appellant versus The Assistant Executive Engineer, Distribution, Tamil Nadu Electricity Board, TANGEDC), Angalakurichi, Udumalaipet Distribution Circle, Tirupur District.
...
Respondent PRAYER: Writ Appeal filed under Clause 15 of the Letter Patent against the order dated 29.08.2019 in W.P. No.29495 of 2011. For Appellant : Mr.S.Murugan 1/4
JUDGMENT
(Judgment of the Court was delivered by D.KRISHNAKUMAR, J.) Learned counsel for the appellant/petitioner fairly submitted that the writ court has passed an order, directing the appellant/petitioner to pay the amount mentioned in the impugned notice dated 22.11.2011, after adjusting the amount already paid, if any without BPSC and penalty to the respondent board, pursuant to which the demanded amount has been paid and electricity connection has been restored by the electricity board.
2. In view of the order passed by the writ court having been complied with, no further adjudication is required. Consequently, the writ appeal stands dismissed as infructuous. There will be no order as to costs. Consequently, connected C.M.P.No.4113 of 2020 is closed. [D.K.K., J.] [P.B.B., J.] 17.07.2023 Index : Yes/No mrn To 2/4
The Assistant Executive Engineer, Distribution, Tamil Nadu Electricity Board, TANGEDC), Angalakurichi, Udumalaipet Distribution Circle, Tirupur District.
3/4
D.KRISHNAKUMAR, J.
and P.B. BALAJI, J.
(mrn) 17.07.2023 4/4