← Library
Madras High CourtWP/12372/2018disposed of

S.A.Kuppusamy, v. The State Of Tamil Nadu,

2018-06-08Honourable The Chief Justice,Honourable Ms. Justice P.T. Asha3 pages

IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED: 08.06.2018 CORAM :

The Hon'ble Ms.INDIRA BANERJEE, CHIEF JUSTICE AND The Hon'ble Ms.JUSTICE P.T.ASHA W.P. No.12372 of 2018 S.A.Kuppusamy .. Petitioner -vs1.The State of Tamilnadu, Rep. by Secretary to Govt., PWD (No.1) Dept., Fort St. George, Chennai 600 009.

2.The District Collector, Namakkal District, Namakkal.

3.The District Revenue Officer, Namakkal.

4.The Revenue Divisional Officer, Thiruchengode, Namakkal District.

5.The Project Director, National Highways, Thiruvakoundanur Post, Junction Main Road, Salem 636 005.

6.The Superintending Engineer, Tamilnadu Electricity Board, Mohanur Road, Namakkal.

7.The District Forest Officer, Collectorate, Namakkal.

8.The Chief Engineer, Public Works Department, Water Resources, Trichy zone, Trichy.

9.Sri.K.Shanmugam, President, Sri Vinayagar Siru Vivasayigal Neeretru Paasana Sangam, 77, Pandamangalam Road, Pothanur, Namakkal District.

.. Respondents Petition filed under Article 226 of the Constitution of India praying for issue of Writ of Mandamus to direct respondents 1 to 8 to consider the petitioner's representation dated 19.02.2018 within a stipulated period.

For Petitioner :

Mr.K.Govi Ganesan For Respondents :

Mr.T.N.Rajagopalan 1 to 4, 7 & 8 Govt. Pleader

O R D E R

(Made by Ms.Indira Banerjee, Chief Justice) After hearing the respective parties, the writ petition is disposed of by directing respondent no.2 to consider the petitioner's representation dated 19.02.2018. A copy of the respondent shall be forwarded to respondent no.2 and respondent no.2 shall take such decision on the representation in accordance with law, as he might deem appropriate, within six

(6) weeks from the date of receipt thereof. No costs. Sd/- Assistant Registrar(CS II) //True Copy// Sub Assistant Registrar sra To 1.The Secretary to Govt. of Tamilnadu, PWD (No.1) Dept., Fort St. George, Chennai 600 009.

2.The District Collector, Namakkal District, Namakkal.

3.The District Revenue Officer, Namakkal.

4.The Revenue Divisional Officer, Thiruchengode, Namakkal District.

5.The Project Director, National Highways, Thiruvakoundanur Post, Junction Main Road, Salem 636 005.

6.The Superintending Engineer, Tamilnadu Electricity Board, Mohanur Road, Namakkal.

7.The District Forest Officer, Collectorate, Namakkal.

8.The Chief Engineer, Public Works Department, Water Resources, Trichy zone,Trichy.

+1cc to Mr.K.Govi Ganesan, Advocate in sr.no.35997 +1cc to Government Pleader in sr.no.36042 W.P.No.12372 of 2018 sr(co) nr 18/06/2018