Bharath Building Construction (India) Pvt Ltd. v. Mrs.V.Gnanarajapushpam
C.M.P. Nos. 4902 and 4909 of 2021 in O.S.A. S.R. 132773 and 132774 of 2019 C.M.P. Nos. 4902 and 4909 of 2021 in O.S.A. S.R. 132773 and 132774 of 2019 N.KIRUBAKARAN, J.
and P.D.AUDIKESAVALU, J.
[Order of the Court was made by N.KIRUBAKARAN, J.,] These Petitions have been filed to condone the delay of 381 days in representing the above Appeals.
2.Heard the Learned Counsel for the Petitioner / Appellant. This Court is convinced with the reasons stated in the respective affidavits filed in support of the respective Petitions to condone the delay of 381 days in representing the above Appeals and accordingly, these Petitions are ordered. [N.K.K.,J.] [P.D.A.,J.] 12.03.2021 ay/Maya Note: Registry is directed to number these appeals, if they are otherwise in order and post the matter for admission.
N.KIRUBAKARAN, J.
https://www.mhc.tn.gov.in/judis/ 1/2
C.M.P. Nos. 4902 and 4909 of 2021 in O.S.A. S.R. 132773 and 132774 of 2019 and P.D.AUDIKESAVALU, J.
ay C.M.P. Nos. 4902 and 4909 of 2021 in O.S.A. S.R. 132773 and 132774 of 2019 Dated:12.03.2021 https://www.mhc.tn.gov.in/judis/ 2/2