IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED : 18.07.2019

CORAM

THE HONOURABLE Mr.JUSTICE M.DHANDAPANI W.P. 25604 of 2009 & M.P.s 1 & 2 of 2009 and W.P. 25605 of 2009 & M.P.s 1 & 2 of 2009 M/s.Amarjothi Spinning Mills Ltd.

Unit B, rep. by its Chairman, Mr.N.Rajan, S/o. C.K.Narayanasamy, Pudusuripalayam, Nambiyur-638 458.

... Petitioner in both W.P.s Vs

1. Tamil Nadu Electricity Board, rep. by its Chairman, Anna Salai, Chennai-600 002.

2. The Superintending Engineer, Tamil Nadu Electricity Board, No.36, Kutchery Street, Gobi Electricity Distribution Circle, Gobichettipalayam.

3. The Superintending Engineer, Udumalpet Electricity Distribution Circle, Udumalpet.

4. The Superintending Engineer, Tirunelveli Electricity Distribution Circle, Tamil Nadu Electricity Board, Tirunelveli - 627 011.

5. The Deputy Financial Controller/ Gobi, No.36, Kutchery Street, Gobi Electricity Distribution Circle, Gobichettipalayam.

... Respondents in both W.P.s

PRAYER in W.P. 25604 of 2009 : Writ Petition filed under Article 226 of the Constitution of India, praying to issue a Writ of Certiorarified Mandamus, calling for the records relating to the electricity bill dated 30.11.2009 passed by the 5th respondent in respect of service connection bearing No.HTSC 85 in the name of the petitioner and quash the same in so far it relates to the consumption charges claimed in clause 1 to 3 of the bill and consequently direct the respondents either to refund the amount or adjust the same in the future electricity bills. PRAYER in W.P. 25605 of 2009 : Writ Petition filed under Article 226 of the Constitution of India, praying to issue a Writ of Certiorarified Mandamus, calling for the records relating to the electricity bill dated 30.11.

2009 passed by the 5th respondent in respect of service connection bearing No.HTSC 36 in the name of the petitioner and quash the same in so far it relates to the consumption charges claimed in clause 1 to 3 of the bill and consequently direct the respondents either to refund the amount or adjust the same in the future electricity bills. For Petitioner : Mr.G.Ethirajulu For Respondents: Mr.P.R.

O R D E R

Today, when these matters were taken up for hearing, the learned counsel appearing for the petitioner would submit that since already the respondents Board has adjusted the amount as per Energy Wheeling Agreement, no further relief sought for is required in these Writ Petitions. Hence, he prayed to dismiss these Writ Petitions as infructuous.

2. In view of the above, as no further adjudication is required in these Writ Petitions, the present Writ Petitions are dismissed as infructuous. No costs. Consequently, connected Miscellaneous Petitions are closed.

-s/d- Assistant Registrar(CS-I) True Copy Sub-Assistant Registrar rpp

To

1. The Chairman, Tamil Nadu Electricity Board, Anna Salai, Chennai-600 002.

2. The Superintending Engineer, Tamil Nadu Electricity Board, No.36, Kutchery Street, Gobi Electricity Distribution Circle, Gobichettipalayam.

3. The Superintending Engineer, Udumalpet Electricity Distribution Circle, Udumalpet.

4. The Superintending Engineer, Tirunelveli Electricity Distribution Circle, Tamil Nadu Electricity Board, Tirunelveli - 627 011.

5. The Deputy Financial Controller/ Gobi, No.36, Kutchery Street, Gobi Electricity Distribution Circle, Gobichettipalayam.

W.P.s 25604 & 25605 of 2009 and M.P.s 1 & 2 of 2009 PPA(CO) SP(22/08/2019)