Madras High CourtC.S(COMM DIV)/104/2022dismissed as settled out of court

M/S Ge.Power Conversion India Private Limited v. M/S Experienced Hi-Tech Consultancy Service (P) Limited

2024-03-20Honourable Mr Justice Abdul Quddhose1 pages

C.S.(COMM.DIV.) No.104 of 2022 P.VELMURUGAN. J.

Today (26.04.2024), the matter is listed under the caption "for reporting compliance".

2. When the matter is taken up for hearing today, the learned counsel for the plaintiff submitted that as per the Joint Memorandum of Compromise dated 18.03.2024, the defendant has paid the second tranche of payment to the plaintiff.

The same is recorded.