S. Rajesh v. Mr. A. V. Ravi
Cont.P.No.1165 of 2018
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED : 15.12.2022
CORAM:
THE HONOURABLE MRS.JUSTICE J.NISHA BANU Cont.P.No.1165 of 2018 S.Rajesh S/o P.Shanmugam (Late) ... Petitioner Vs.
1.Mr.A.V.Ravi The Chief Engineer (Personnel) North Madras Thermal Power Project North Chennai, Chennai - 600 057.
...
Respondent Prayer: Petition filed under Section 11 of the Contempts of Court Act, 1971, to punish the respondent herein for willful disobedience of the order of this Court made in W.P.No.4017 of 2015 dated 19.10.2016. For Petitioner : Mr.K.Krishnamoorthi For Respondents : Mr.Anand Gopalan for M/s T.S.Goplalan & Co., 1 / 2 https://www.mhc.tn.gov.in/judis
Cont.P.No.1165 of 2018 J.NISHA BANU , J.
Jer
ORDER
Today, when the matter is taken up for hearing, the learned counsel for the petitioner as well as the learned counsel for the respondent would state that the orders passed in W.P.No.4017 of 2015 dated 19.10.2016 has been complied with.
2.Considering the submissions of the learned counsel for the petitioner as well as the learned counsel for the respondent, this Contempt Petition is closed.
15.12.2022 Index : Yes / No Internet : Yes / No Jer To The Chief Engineer (Personnel) North Madras Thermal Power Project North Chennai, Chennai - 600 057.
Cont.P.No.1165 of 2018 2 / 2 https://www.mhc.tn.gov.in/judis