IN THE HIGH COURT OF JUDICATURE AT MADRAS

Dated : 09.07.2025

CORAM

THE HONOURABLE Ms. JUSTICE P.T. ASHA W.P.No. 4020 of 2021 & W.M.P.Nos. 4593 & 7302 of 2021 Royal Enfield A unit of Eicher Motors Ltd., Thiruvottiyur High Road, Thiruvottiyur, Chennai - 600 019 Rep. by its Authorised Signatory

...Petitioner

Vs.

1.The Additional Commissioner of Labour, Labour Welfare Building, Teynampet, Chennai - 6.

2.Royal Enfield Employees Union, Regd. No. 3617 / CNI No.5, Dr. Vasudevan Road, Kilpauk, Chennai - 600 010.

1/6

3.Oragadam Royal Enfield Employees General Union, A - 19/1, SIPCOT Industrial, Growth Center, Oragadam, Kanchipuram Dt., Tamil Nadu 602 105

...Respondents

Prayer: Writ Petition is filed under Article 226 of the Constitution of India to issue a Writ of Mandamus, directing the 1st respondent to consider the preliminary issue of maintainability of the application dated 02.04.2019 in Na.Ka.A/1166/2019 filed by the 2nd respondent taking into consideration the objections and contentions raised by the petitioner in its Application in Ref: HR/001/2021 dated 07.01.2021 before proceeding to adjudicate the application on merits and pass such further or other orders.

For Petitioner :

Mr. Anand Gopalan For M/s. T.S.Gopalan & Co., For Respondent1:

Mrs. M.Jayanthi Additional Government Pleader 2/6

For Respondent 2:

Mr. K.M.Ramesh Senior Counsel For Mr. V.Subramani For Respondent 3:

No Appearance.

O R D E R

The relief claimed in this writ petition is as follows: "Directing the 1st respondent to consider the preliminary issue of maintainability of the application dated 02.04.2019 in Na.Ka.A/1166/2019 filed by the 2nd respondent taking into consideration the objections and contentions raised by the petitioner in its Application in Ref: HR/001/2021 dated 07.01.2021 before proceeding to adjudicate the application on merits and pass such further or other orders".

2. However, both the learned counsels consented that it would suffice if the 1st respondent is called upon at the outset to verify as to whether the 2nd respondent union enjoys membership of a considerable 3/6

strength of the employees of the petitioner company. This exercise shall be completed within a period of 3 weeks from the date of receipt of a copy of this order. If the 2nd respondent is able to establish that it has a fairly large strength of the employees, further proceedings shall go on.

3. The Writ Petition is disposed of with the above observations. Consequently, the connected miscellaneous petitions are closed. No costs.

09.07.2025 Index : Yes/No Internet : Yes/No kan 4/6

To The Additional Commissioner of Labour, Labour Welfare Building, Teynampet, Chennai - 6.

5/6

P.T. ASHA, J, kan W.P.No. 4020 of 2021 09.07.2025 6/6