IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED : 06.02.2026

CORAM

THE HONOURABLE Ms. JUSTICE P.T. ASHA Annamalai and Co., Rep by its Partner A Karthikeyan,, S/o. R.Annamalai 10/57-A-1, Thanakuttivalavu, Pachaliyur, Chinnappampatty Post, Edapadi Taluk Salem District ... Petitioner Vs.

1. The Superintending Engineer (Highways) Construction and Maintenance, Salem Circle, Salem.

2. The Divisional Engineer (Highways) Construction and Maintenance, Edappady Division, Salem.

...Respondents

Prayer:- Writ petition filed under Article 226 of the Constitution of India praying for issuance of a writ of Mandamus, directing the 2nd Respondent, to issue "Work Site Inspection Certificate" and "Working Condition of 1/4

Plants & Machineries Certificate" to the Petitioner, enabling them to participate in the e-Tender floated by the 1st Respondent vide tender notice No. 52/2025-2026/HDO dated 19.01.2026, Serial No.3, by considering the Petitioner's representation/ application dated 28.01.2026. For Petitioner : Mr.S.S.SENTHIL For Respondents : Mrs.P.Aishwarya, Govt. Advocate for R.1 and R.2.

O R D E R

The Writ Petition has been filed for the following reliefs:- " directing the 2nd Respondent, to issue "Work Site Inspection Certificate" and "Working Condition of Plants & Machineries Certificate" to the Petitioner, enabling them to participate in the e-Tender floated by the 1st Respondent vide tender notice No. 52/2025-2026/HDO dated 19.01.2026, Serial No.3, by considering the Petitioner's representation/ application dated 28.01.2026."

2. When the matter came up for hearing, the learned Government Advocate appearing on behalf of the respondents on instruction would submit that "Work Site Inspection Certificate" and "Working Condition of Plants & Machineries Certificate" would be issued today, if all other parameters are in order.

2/4

3. Recording the same, the Writ Petition is disposed of. No costs. 06.02.2026 (shr) Index : Yes/No Speaking Order: Yes/No To

1. The Superintending Engineer (Highways) Construction and Maintenance, Salem Circle, Salem.

2. The Divisional Engineer (Highways) Construction and Maintenance, Edappady Division, Salem.

3/4

P.T. ASHA . J., (shr) 06.02.2026 (4/4) 4/4