The Executive Engineer And Administrative Officer v. G. Pushpam
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 08.04.2026
CORAM
THE HON'BLE MR.SUSHRUT ARVIND DHARMADHIKARI, CHIEF JUSTICE AND THE HON'BLE MR.JUSTICE G.ARUL MURUGAN CMP No. 3717 of 2026 in WA SR No.122119 of 2024
1. The Executive Engineer and Administrative Officer Tamil Nadu Housing Board, Coimbatore Housing Unit, HUDCO Colony, Peelamedu, Coimbatore 12.
Applicant Vs
1. G. Pushpam Legal heirs of Gopalsamy, No.107, Patel Street, Ayyanthottam, Opp.
Lakshmi Mill Works, Kalapatti, Coimbatore. And 5 others Respondent(s) For Applicant:
Mr. M.Arunkumar https://www.mhc.tn.gov.in/judis
The Hon'ble Chief Justice and G.Arul Murugan, J.
ORDER
(Order of the Court was made by the Hon'ble Chief Justice) Heard learned counsel for the applicant.
2. This is an application for condonation of delay of 464 days in re-presenting the appeal papers.
3. Taking into consideration the cause shown, we are inclined to condone the delay.
Accordingly, the delay is condoned and the application is allowed.
(SUSHRUT ARVIND DHARMADHIKARI, CJ.) (G.ARUL MURUGAN, J.) 08.04.2026 sra CMP No.3717 of 2026 in WA SR No.122119 of 2024 https://www.mhc.tn.gov.in/judis