Cholamandalam Investment And Finance Co Ltd v. Kamar Infrastructure Private Limited
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 18-06-2026
CORAM
THE HON'BLE MR.JUSTICE K.KUMARESH BABU Arb.Appln. No.204 of 2026 M/s.Cholamandalam Investment and Finance Company Limited, 'Chola Crest', C 54 & 55, Super B-4, Thiru Vi Ka Industrial Estate, Guindy, Chennai - 600 032.
Represented by its Authorised Signatory ..Applicant Vs M/s.Kamar Infrastructure Private Limited, Kamar Estate Devicha Pada Taloja Mide Panvel Raigarh, Behind Deepak Nitrate Ltd., Panvel, Maharashtra - 410 208.
..Respondent Arbitration Application filed under Order XIV Rule 8 of Original Side Rules r/w.Section 9(1)(ii)(a)(b)(d) & (e) of the Arbitration and Conciliation Act, 1996, praying to appoint employee of the applicant viz., Mr.Partha Bhattacharya, Regional Legal Manager, as receiver to seize and take possession of the vehicle which is more fully described in the schedule to the Judges Summons which is lying in the custody of the respondent or respondent's men, agents, servants from respondent premises or wherever found with police aid and break open of premises if necessary.
For Petitioner :
Mr.D.Pradeep Kumar ****
O R D E R
By order dated 11.02.2026, this Court had appointed a Party-Receiver.
2. Notice had also been served upon the respondent, representing whom a counsel had also filed vakalat, but for the deficiencies noted, the same had been returned.
3. Today when the matter is taken up, there is no representation on the side of the respondent nor the respondent is present.
4. In view of the same, this application stands ordered as prayed for, making absolute the order dated 11.02.2026. No costs. 18-06-2026 kak
K.KUMARESH BABU, J.
kak Arb.Appln.No.204 of 2026 Dated : 18-06-2026