M.Natarajan v. The Collector
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED : 23.10.2019 CORAM :
THE HONOURABLE MR.JUSTICE N.KIRUBAKARAN and THE HONOURABLE MR.JUSTICE P.VELMURUGAN W.A.No.729 of 2019 and C.M.P.No.5894 of 2019 M.Natarajan ... Appellant Vs 1.The Collector, Kancheepuram District.
2.The Tahsildar, Pallavaram Taluk, Kancheepuram District.
3.The Chairman, Tamil Nadu Electricity Board, 800, Anna Salai, Chennai 600 002.
4.The Executive Director, TANGEDCO, Chennai 600 002.
5.The Chief Engineer (South) Tamil Nadu Electricity Board, Chennai 600 002.
6.The Superintendent Engineer (South) Tamil Nadu Electricity Board, K.K.Nagar, Chennai 600 078.
7.The Executive Engineer (Maintenance) Tamil Nadu Electricity Board, Porur, Chennai 600 116.
8.The Assistant Engineer, Tamil Nadu Electricity Board, Somangalam, Chennai 600 069.
... Respondents
PRAYER : Appeal against the order of this Court in W.P.No.4308 of 2018 dated 07.12.2018.
Wp.4308 of 18: Petition filed Under Article 226 of the Constitution of India praying to issue a Writ of Certiorarified Mandamus to call for the entire records pertaining to the order passed by the 8th respondent in his proceedings f/vz;/c/kP/bgh/,&g/nrhk/nfhtpt No. 156/2017 dated 07.11.2017 and quash the same and directed the authorities concerned to restore the electricity connection to the petitioner so as to enable him to carryout cultivating works over the schedule mentioned property. For Appellant : Mr.M.Natarajan (party in person) For Respondents : Mr.J.Pothiraj, (for R1 & R2) Special Government Pleader Mr.S.K.Rameshuwar (for R3 to R8) Standing counsel
J U D G M E N T
(Judgment of the Court was delivered by N.KIRUBAKARAN, J) The Appeal has been filed against the order passed in W.P.No.4308 of 2018 dated 07.12.2018.
2.It is submitted by the learned counsel appearing on behalf of the TANGEDCO that as per the earlier order passed by this Court on 16.10.2019, the free electricity connection has been restored to the appellant. The appellant who is appearing as party in person has also confirmed the same. 3.With regard to the change of name in respect of the electricity connection, the appellant is directed to give a representation with details of the property. On such application, the respondent shall change the name of the consumer in respect of the electricity connection, within a period of two weeks from the date of receipt of a copy of this order. 4.With the above direction, the Writ Appeal is disposed of. No costs. Consequently, connected Miscellaneous Petitions is closed.
Sd/- Assistant Registrar //True Copy// Sub Assistant Registrar
sai To 1.The Collector, Kancheepuram District.
2.The Tahsildar, Pallavaram Taluk, Kancheepuram District.
3.The Chairman, Tamil Nadu Electricity Board, 800, Anna Salai, Chennai 600 002.
4.The Executive Director, TANGEDCO, Chennai 600 002.
5.The Chief Engineer (South) Tamil Nadu Electricity Board, Chennai 600 002.
6.The Superintendent Engineer (South) Tamil Nadu Electricity Board, K.K.Nagar, Chennai 600 078.
7.The Executive Engineer (Maintenance) Tamil Nadu Electricity Board, Porur, Chennai 600 116.
8.The Assistant Engineer, Tamil Nadu Electricity Board, Somangalam, Chennai 600 069.
+2cc to Mr.M.Natarajan, party in person, SR.88493 W.A.No.729 of 2019 CA(CO) CB(07/11/2019)