IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED : 01.03.2024

CORAM

THE HON'BLE MR. JUSTICE P.D. AUDIKESAVALU M/s. Karthikeyan Constructions, Rep. by its Managing Partner, C.Senthilkumar 4/120 Jallyhali Kottai, Chettikarai Post, Dharmapuri TK & District.

... Petitioner -vsThe Forest Engineer, Forest Engineer Division, Harur, Dharmapuri District.

... Respondent Prayer:- Writ Petition filed under Article 226 of the Constitution of India, 1950, praying to issue a Writ of Mandamus, directing the Respondents consider the Petitioner's application dated 18.02.2024 and issue machinery certificate. For Petitioner : Mr. A.Elamparithi For Respondent : Mr. S.Rajesh, Government Advocate

O R D E R

Heard Mr. A.Elamparithi, Learned Counsel for the Petitioner and Mr. S.Rajesh, Learned Government Advocate, who takes notice for the Respondent and perused the materials placed on record, apart from the 1/3

pleadings of the parties.

2.

The Writ Petition has been filed for directing the Respondent to consider application dated 18.02.2024 made by the Petitioner to issue machinery certificate.

3.

It is informed by Learned Government Advocate appearing for the Respondent that the machinery certificate dated 01.03.2024 has been granted to the Petitioner and its copy has been placed on record. Learned Counsel for the Petitioner also acknowledges its receipt in court today. In view of the same, nothing remains for consideration in the Writ Petition. In fine, the Writ Petition is disposed. No costs. 01.03.2024 Index: Yes/No NCC: Yes/No Note: Issue order copy by 03.04.2024.

kv To The Forest Engineer, Forest Engineer Division, Harur, Dharmapuri District.

2/3

P.D. AUDIKESAVALU, J.

kv 01.03.2024 3/3