Kavitha v. The Superintending Engineer
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 16.02.2026
CORAM
THE HON'BLE MR.JUSTICE V. LAKSHMINARAYANAN WP No.6317 of 2026 and WMP.No.6810 of 2026 Kavitha ..Petitioner(s) Vs 1.The Superintending Engineer, Special Project, Department 4th Floor, Kalaignar Maaligai, Ripon Building, Chennai 600 003.
2.The Executive Engineer (Zone 10), Special Project, Department 4th Floor, Kalaignar Maaligai, Ripon Building, Chennai 600 003.
..Respondent(s) Prayer: Writ Petition is filed under Article 227 of the Constitution of India for a writ of Mandamus thereby direct the respondents to issue the Site Visit Certificate to enable the petitioner to participate in the works covered in etender notice nos.S.P.D.C.No.B1/0172-1/2026 PACKAGE 1, S.P.D.C.No.B1/0172-2/2026 PACKAGE 2, S.P.D.C.No.B1/0183-5/2026 PACKAGE 5, S.P.D.C.No.B1/0183-6/2026 PACKAGE 6, dated 18.02.2026 and in the alternate to direct the 1st respondent to accept the tender documents to be uploaded by the petitioner without insisting for the production of Site Visit Certificate from the respondents for the above said works. For Petitioner(s):
Ms.Athiniveda For Respondent(s):
Mr.E.C.Ramesh, Standing Counsel
Order The petitioner proposed to participate in a tender called by the respondent. Her staff approached the respondents and requested them to issue a Site Visiting Certificate, which is necessary enclosure to participate in the tender. As the same has not been issued, the petitioner is before this Court. 2.When the matter was mentioned this morning, I informed Ms.Athiniveda, to serve papers on Mr.Ramesh. Mr.Ramesh has been instructed by the Superintendent Engineer, Special Project Department, Chennai, Greater Chennai Corporation that the corrigendum has been issued. The same is scanned and extracted hereunder:
3. Mr.Ramesh states that the Corrigendum has been issued extending the late date for Site Visit request till 17.02.2026 and for issuance of the Site Visiting Certificate by 19.02.2026. Hence, the Site Visit Certificate for the petitioner will be issued by 18.02.2026. His statement is recorded. Writ Petition has been disposed of. No costs. Consequently connected miscellaneous petitions are closed.
16.02.2026 Index: Yes/No Speaking/Non-speaking order sk To 1.The Superintending Engineer, Special Project, Department 4th Floor, Kalaignar Maaligai, Ripon Building, Chennai 600 003.
2.The Executive Engineer (Zone 10), Special Project, Department 4th Floor, Kalaignar Maaligai, Ripon Building, Chennai 600 003.
V.LAKSHMINARAYANAN J.
sk WP No. 6317 of 2026 and WMP.No.6810 of 2026 16.02.2026