← Library
Madras High CourtWP/31707/2014withdrawn dismissed

R.S.Yarns And Power Private v. Tamilnadu Electricity

2016-04-29Honourable Mr Justice T. S. Sivagnanam2 pages

IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATE: 29.04.2016

CORAM

THE HONOURABLE MR.JUSTICE T.S.SIVAGNANAM W.P.No.31707 of 2014 & M.P.No.2 of 2014 R.S.Yarns and Power Private Limited, WIND FARM HT SC No.3124, 40(1), S.V.Colony East, 9th Street, P.N.Road, Tirupur-641 602, Rep. by its Director S.Babu.

.. Petitioner

Versus

1.Tamil Nadu Electricity Regulatory Commission rep. by its Secretary, 19-A, Rukmini Lakshmipathy Salai, (Marshall's Road), Egmore, Chennai-600 008.

2.Tamil Nadu Generation and Distribution Corporation Limited, Rep. by its Director, 800, Anna Salai, Chennai-600 002.

3.The Chief Engineer (NCES), TANGEDCO Limited, 800, Anna Salai, Chennai-600 002.

4.The Superintending Engineer, Tirunelveli Electricity Distribution Circle, TANGEDCO Limited, Tirunelveli.

.. Respondents Prayer: The Writ Petition is filed under Article 226 of the Constitution of India, seeking for a Writ of Certiorarified Mandamus, to call for the records of the third respondent in his impugned proceedings bearing Lr.No.CE/NCES/SE/EE/WPP/ A2/F.Third Party Sale / D.1171/14, dated 25.09.2014, quash the same as arbitrary, illegal and against the Orders passed by the first respondent in T.L.A.No.1 of 2011, dated 16.11.2012, Tariff Order No.1 of 2009, dated 20.03.2009, Tariff Order No.6 of 2012, dated 31.07.2012 and Intra State Open Access Regulations, 2005 and consequently, direct the third respondent to permit the petitioner to sell the wind energy generated in their wind mill WF HT SC No.3124 through the trading license issued by the first respondent in T.L.A.No.1 of 2011, 16.11.2012.

https://hcservices.ecourts.gov.in/hcservices/

For Petitioner : Mr.M.Saravanakumar For Respondents : Mr.S.K.Raameshuwar Standing Counsel

O R D E R

The learned counsel appearing for the petitioner has given a letter dated 25.04.2016 to the Registry seeking for direction to withdraw the Writ Petition.

2. Accordingly, this Writ Petition has been posted today before this Court for withdrawal.

3. This Writ Petition is therefore dismissed as withdrawn. No costs. Consequently, connected petition is closed.

Sd/- Assistant Registrar(CS-VI) //True Copy// Sub Assistant Registrar rpa To

1. The Secretary, Tamil Nadu Electricity Regulatory Commission, 19-A, Rukmini Lakshmipathy Salai, (Marshall's Road), Egmore, Chennai-600 008.

2.The Director, Tamil Nadu Generation and Distribution Corporation Limited, 800, Anna Salai, Chennai-600 002.

3.The Chief Engineer (NCES), TANGEDCO Limited, 800, Anna Salai, Chennai-600 002.

4.The Superintending Engineer, Tirunelveli Electricity Distribution Circle, TANGEDCO Limited, Tirunelveli.

W.P.No.31707 of 2014 & M.P.No.2 of 2014 ak co kra 31.05.2016 https://hcservices.ecourts.gov.in/hcservices/