Cheran Foundation Trust v. The District Collector
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 01.04.2024
CORAM:
THE HONOURABLE MR. JUSTICE G.K.ILANTHIRAIYAN Cheran Foundation Trust Rep. By its Authorized Signatory, No.78, Cheran Tower, Arts College Road, Coimbatore 641 018 ... Petitioner Vs.
1.The District Collector, Office of the Collector, Coimbatore 641 018 2.The District Revenue Officer, Gopala Puram, Coimbatore, Tamilnadu 641 018 3.The Assistant General Manager, Power Grid Corporation of India Ltd., Avinashi Coimbatore Road, Opp to Senni Andavar kovil Road, Karumanthampatti, Tamilnadu 641 659 ... Respondents PRAYER:
Writ Petition is filed under Article 226 of Constitution of India praying to issue a Writ of Mandamus directing the third respondent to act in accordance with the directives issued by the second respondent in its 1/6
letter dated 07.05.2021 in Oo.Mu.6933/2021/E2. For Petitioner : M/s.V.Srimathi For Respondents For R1 & 2 : Mr.S.J.Mohamed Satik, Government Advocate For R3 : Mr.V.Kalyanaraman for M/s.Aiyar and Dolia
O R D E R
This writ petition has been filed for direction to the third respondent to act in accordance with the directions issued by the second respondent dated 07.05.2021.
2.
The petitioner Trust owned land admeasuring 51 acres comprised in survey no.120, Kattampatti Village, Kinathukadavu Taluk, Coimbatore District. While being so, the first respondent had issued an order empowering the third respondent vide order dated 06.02.2020 to enter upon the land of the petitioner for erection of electric pylons. The petitioner also objected the same. However, the said objection was overruled and as such, the petitioner challenged the said order by way of writ petition before this Court in WP.No.12470 of 2020. This Court 2/6
directed to consider the objections raised by the petitioner and to pass orders in accordance with law. Thereafter, the first respondent suggested two alternative proposals for placement of pylon on the petitioner's land. Thereafter, the first respondent issued notice to the petitioner dated 12.11.2020. On the said notice, the petitioner submitted representation and requested to issue stop work notice to the third respondent. However, the said request was not considered and the third respondent had erected towers. The petitioner was paid compensation of Rs.35,80,906/- and the same was received with protest.
3.
Thereafter, the petitioner sought for enhancement of compensation and filed representation to the second respondent. In turn, it was forwarded to the third respondent. As per Section 16(3) of the Indian Telegraph Act, 1885, if any dispute arises concerning the sufficiency of the compensation to be paid under section 10, clause (d), it shall, on application for that purpose by either of the disputing parties to the District Judge within whose jurisdiction the property is situate, be determined by him. Therefore, the third respondent cannot act as an 3/6
authority to enhance the compensation. Hence, the request made by the petitioner cannot be considered by the third respondent. That apart, the request was simply forwarded by the second respondent to the third respondent. Therefore, the prayer sought for in this writ petition cannot be considered. As such, this writ petition is devoid of merits and liable to be dismissed.
4.
Accordingly, this writ petition is dismissed. However, the petitioner is at liberty to approach the competent court for enhancement of compensation in the manner known to law, if so advised. There shall be no order as to costs.
01.04.2024 Index: Yes/No Speaking/Non-speaking order lok 4/6
To 1.The District Collector, Office of the Collector, Coimbatore 641 018 2.The District Revenue Officer, Gopala Puram, Coimbatore, Tamilnadu 641 018 3.The Assistant General Manager, Power Grid Corporation of India Ltd., Avinashi Coimbatore Road, Opp to Senni Andavar kovil Road, Karumanthampatti, Tamilnadu 641 659 G.K.ILANTHIRAIYAN, J.
lok 5/6
01.04.2024 6/6