← Library
Madras High CourtOP/204/2017dismissed as withdrawal

M/S.Consolidated Construction v. Maruti Suzuki India Limited

2017-06-22Honourable Dr Justice Anita Sumanth3 pages

IN THE HIGH COURT OF JUDICATURE AT MADRAS

Dated : 22.06.2017 Coram The Honourable MR. JUSTICE Dr.ANITA SUMANTH Original Petition No.204 of 2017 M/s.Consolidated Construction Consortium Limited rep. by its authorised Signatory Mr.S.Raghavendran .. Petitioner vs.

Maruti Suzuki India Limited Gurgaon Plant, Palam Gurgaon Road, Gurgaon - 122015, Haryana, INDIA.

.. Respondent Petition filed under sections 11 of the Arbitration and Conciliation Act, 1996, seeking an order to appoint a sole arbitrator to adjudicate the dispute between the petitioner and the respondents in accordance with Section 11 of the Arbitration and Conciliation Act, 1996 and to pay costs.

For Petitioner : Mr.S.S.Rajesh

O R D E R

The learned counsel for the petitioner seeks permission of this court to withdraw the Original Petition and he has also made an endorsement to that effect in the bundle.

Dr.ANITA SUMANTH, J., smi

2. In view of the same, the Original Petition stands dismissed as withdrawn.

22.06.2017 smi O.P.No.204 of 2017