IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED : 13.08.2024 CORAM :

THE HONOURABLE MR. JUSTICE M. DHANDAPANI S.Selvakumar ... Petitioner Vs.

1.The Executive Engineer, O & M, Tamilnadu Generation and Distribution Corporation Limited (TANGEDCO), Udumalpet Road, Pollachi - 642 001.

2.The Assistant Executive Engineer, O & M, Tamilnadu Generation and Distribution Corporation Limited (TANGEDCO), Udumalpet Road, Pollachi - 642 001.

3.The Assistant Engineer / Junior Engineer, Rural Section, Tamilnadu Generation and Distribution Corporation Limited (TANGEDCO), Udumalpet Road, Pollachi - 642 001.

4.M.Sabapathy [R4 impleaded vide order dt. 28.04.2021 made in W.M.P.No.10411 of 2021 in W.P.No.5783 of 2018] ... Respondents Prayer : Writ Petition filed under Article 226 of the Constitution of India praying for issuance of Writ of Certiorarified Mandamus, to call for Page No.1 of 4

the records of the 3rd respondent's Letter No.J.E./Rural/Po/File Complaint petition/A.No.262/17-18 dated 01.03.2018, quash the same by directing the respondents not to give any new electricity connection in the petitioner's agriculture land in Electricity Service Connection No.526. For Petitioner : Mr.B.Thirumalai For Respondents : Mr.L.Jai Venkatesh Standing Counsel [R1 to R3] Mr.K.J.Parthasarathy [R4] *****

ORDER

When the matter is taken up for hearing today, learned Standing Counsel appearing for the respondents 1 to 3 submitted that, though the petitioner has filed the present writ petition challenging the 3rd respondent's Letter No.J.E./Rural/Po/File Complaint petition/A.No.262/17-18 dated 01.03.2018 rejecting the petitioner's objection and stating that they are going to give new electricity connection to the 4th respondent from the electricity post connection No.526 situated in the petitioner's agriculture land, however, during the pendency of the writ petition, new electricity service connection was effected in favour of the 4th respondent and now, the 4th respondent is paying the electricity charges to the official respondents/Electricity Page No.2 of 4

Board.

2. In view of the above submissions made by the learned Standing Counsel appearing for the respondents 1 to 3, nothing survives for adjudication in this writ petition. Accordingly, this writ petition is dismissed as infructuous. No costs.

13.08.2024 Index : Yes / No Speaking order / Non-speaking order sp To 1.The Executive Engineer, O & M, Tamilnadu Generation and Distribution Corporation Limited (TANGEDCO), Udumalpet Road, Pollachi - 642 001.

2.The Assistant Executive Engineer, O & M, Tamilnadu Generation and Distribution Corporation Limited (TANGEDCO), Udumalpet Road, Pollachi - 642 001.

3.The Assistant Engineer / Junior Engineer, Rural Section, Tamilnadu Generation and Distribution Corporation Limited (TANGEDCO), Udumalpet Road, Pollachi - 642 001.

Page No.3 of 4

M.DHANDAPANI, J.

sp 13.08.2024 Page No.4 of 4