M/S.Fabtech International Hosieries Pvt Ltd v. The Chairman

2021-04-01Honourable Mr Justice B.Pugalendhi3 pages

IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED : 1/4/2021 C O R A M THE HONOURABLE Mr.JUSTICE B.PUGALENDHI Writ Petition No.8538 of 2021 M/s.Fabtech Internatinoal Hosieries Pvt Ltd rep. By its Authorised Signatory Mr.V.Kirubakar ...

Petitioner Vs

1. The Chairman TANGEDCO 144 Anna Salai Chennai 600 002.

2. The Chief Engineer, NCES TANGEDCO II Floor 144 Anna Salai Chennai 600 002.

3. The Superintending Engineer TANGEDCO Theni EDC Theni.

...

Respondents Petition filed under Article 226 of the Constitution of India praying for the issuance of a writ of mandamus to direct the respondents for the termination of the Power Purchase Agreement dated 28/3/2017 and to execute Energy Wheeling Agreement for captive consumption under the preferential tariff scheme.

For petitioner ...

Mr.T.Chezhiyan For respondents ...

Mr.N.Damodaran Standing Counsel TANGEDCO - - - - - -

O R D E R

This writ petition has been filed to direct the respondents for the termination of the Power Purchase Agreement dated 28/3/2017 and to execute Energy Wheeling Agreement for captive consumption under the preferential tariff scheme.

2. The case of the petitioner Company is that energy generated by the windmills of the petitioner Company was sold to the respondent TANGEDCO by executing an Energy Purchase Agreement dated 28/3/2017. Though the petitioner had supplied

wind energy,TANGEDCO delayed the payments and therefore, they have opted to convert the existing EPA to EWA for the purpose of allowing the captive consumption. The same was objected by the Board and therefore, batch of writ petitions filed before this Court in W.P.No.5196 of 2019 and this Court, by an order, dated 30/8/2019, allowed those writ petitions, on the following directions:- "29. Thus, for the reasons stated above, the writ petitions deserve to be allowed with the following directions:- (a).

the respondents/TANGEDCO are directed to permit the petitioners to switch over to captive consumption so as to use the same for their own industry;

(b).

the respondents/TANGEDCO are directed to settle the respective dues to the petitioners as per their respective invoices raised by them, along with interest as per Clause 6 (b), within a period of two months from the date of receipt of a copy of this order.

As against the orders of this Court, writ appeals were also filed and the writ appeals were dismissed and the SLP preferred by the Board also dismissed and the issue has been settled that the petitioners are entitled for migration are utilised the same captive consumption.

3. In the instant case, the petitioner has sought for migration for captive consumption and the same is pending with the respondents. Therefore, the writ petition was filed. In view of the earlier orders passed, this writ petition is also allowed, on the same directions, issued in W.P.No.5186 of 2019, batch. With regard to the consideration for the application for migration, the same may be processed by the TANGEDCO, within a period of four weeks from the date of receipt of a copy of this order. No costs. Consequently, the connected Miscellaneous Petition is closed.

Sd/- Assistant Registrar(CS IX) //True Copy// Sub Assistant Registrar mvs.

TO,

1. The Chairman TANGEDCO 144 Anna Salai Chennai 600 002.

2. The Chief Engineer, NCES TANGEDCO II Floor 144 Anna Salai Chennai 600 002.

3. The Superintending Engineer TANGEDCO Theni EDC Theni.

Writ Petition No.8538 of 2021 pch (CO) A.SK(08.07.2021)