V.Natarajan v. S.K.Ramachandran
CMP NO. 8381 of 2025
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 16-10-2025
CORAM
THE HONOURABLE MR.JUSTICE P.B. BALAJI CMP NO. 8381 of 2025 AND CRP SR NO. 36020 OF 2025 V.Natarajan Appellant(s) Vs S.K.Ramachandran and 2 Others Respondent(s) For Appellant(s): Mr.K.Jothisivam For Respondent(s): Mr.S.Senthil, for R2 Caveator
ORDER
This Civil Miscellaneous Petition has been filed seeking to condone the delay of 27 days in filing the above revision.
2. Heard the learned counsel on either side.
3. I have gone through the affidavit filed in support of this petition for condonation of delay and I find that the petitioner has made out sufficient cause for not being able to file the revision within the statutory time of limitation. Hence, I am inclined to allow this application.
4. Accordingly, this Civil Miscellaneous Petition is ordered and the delay of 27 days in filing the revision is condoned.
https://www.mhc.tn.gov.in/judis
P.B. BALAJI, J.
skt
5. Registry is directed to number the Civil Revision Petition, if the papers are otherwise in order and post the main case for admission in the usual course. 16-10-2025 skt To The Subordinate Judge, Ambattur.
CMP NO. 8381 of 2025 AND CRP SR NO. 36020 OF 2025 https://www.mhc.tn.gov.in/judis