IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED: 10-03-2026

CORAM

THE HON'BLE MR JUSTICE M.DHANDAPANI W.P.No. 9295 of 2026 S.Murugesan S/o. Chinnathambi Gounder 1/86A, Nallagoundampatti Post Chellapillai Kuttai Village Omalur Taluk, Salem District.

...Petitioner(s)

Vs

1. The Superintending Engineer (Operation and Maintenance) TNEB, Udaiyapatti, Salem Salem District.

2. The Assistant Engineer (Operation and Maintenance) Salem Electricity Distribution Circle Vellakalpatti, Karuppur Omalur Taluk, Salem District.

3. The Assistant Engineer (Operation and Maintenance) Corporation, Muthunaickenpatti Omalur Taluk, Salem District.

4. The Executive Engineer Corporation, Kondalampatti Annadanapatti, Salem District.

636010.

...Respondent(s)

PETITION under Article 226 of The Constitution of India praying for the issuance of a Writ of Mandamus to direct the respondents to remove the electricity meter and fuse carriers in three phase commercial electricity connection No.04-460-004-804 from the petitioner's land in survey No.209/2B2 an extent of 35 3/4 cents at Chellapillai Kuttai Village, Omalur Taluk, Salem District by considering the petitioner's representation dated 23.1.2026.

For Petitioner(s):

Mr.G.Vigneshwar For Respondent(s):

Mr.I.Syed Sibghatulla, Standing Counsel

ORDER

This is a petition filed by the petitioner seeking a direction to the

respondents to consider his representation dated 23.1.2026 for removal of the electricity meter and the fuse carriers pertaining to three phase commercial electricity connection No.04-460-004-804 from his land in survey No.209/2B2 measuring an extent of 35 3/4 cents at Chellapillai Kuttai Village, Omalur Taluk, Salem District.

2. Heard the learned counsel for the petitioner and the learned Standing Counsel accepting notice for the respondents.

3. The case of the petitioner is as follows:

(a) The petitioner owns the subject lands. He has acquired the subject lands by way of purchase through a registered sale deed for a valid sale consideration. Ever since the date of purchase, the petitioner is in possession and enjoyment of the same. The joint patta for the subject lands stood in the name of the petitioner as well as his vendor. Later, the petitioner got a separate patta for the subject lands. (b) The petitioner's vendor obtained a three phase commercial electricity connection for manufacturing bricks. Further, the electricity

meter and the fuse carrier were placed in the petitioner's land. This is causing disturbance to the petitioner. Hence, the petitioner sent a representation dated 23.1.2026 to the respondents seeking to remove the electricity meter and the fuse carrier placed in his land. As it did not evoke any response, the petitioner is before this Court.

4. Considering the limited nature of the prayer sought for and without expressing any opinion on the merits of the case, the writ petition is disposed of with a direction to the third respondent to consider the said representation of the petitioner dated 23.1.2026 on merits and pass appropriate orders thereon in accordance with law within a period of four weeks from the date of receipt of a copy of this order. No costs. 10-03-2026 Index: Yes/No Speaking/Non-speaking order

To

1. The Superintending Engineer (Operation and Maintenance) TNEB, Udaiyapatti, Salem Salem District.

2. The Assistant Engineer (Operation and Maintenance) Salem Electricity Distribution Circle Vellakalpatti, Karuppur Omalur Taluk, Salem District.

3. The Assistant Engineer (Operation and Maintenance) Corporation, Muthunaickenpatti Omalur Taluk, Salem District.

4. The Executive Engineer Corporation, Kondalampatti Annadanapatti Salem District 636010.

RLI

M.DHANDAPANI, J.

RLI W.P.No. 9295 of 2026 10-03-2026