Mr.K.S.Baburaj v. The Union Of India
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED 02.07.2019
CORAM
THE HONOURABLE MRS.JUSTICE PUSHPA SATHYANARAYANA O.P.No.314 of 2019 K.S.Baburaj .. Petitioner -vs1.The Union of India, Rep by the General Manager, Southern Railway, Park Town, Chennai - 600 003.
2.The Chief Engineer (East), Construction, Periyar EVR High Road, Construction Complex, Southern Railway, Egmore, Chennai - 600 008.
3.The Deputy Chief Engineer-II, Construction, Southern Railway, Near My Lady's Garden, Park Town, Chennai - 3.
.. Respondents Prayer: Petition filed under Section 11(6) of the Arbitration & Conciliation Act, 1996 to appoint an Arbitrator and refer all the claims arising out of the Agreement No.14/Dy.CE/CN/II/MAS/2016 dated 21.12.2016 to Arbitration.
For Petitioner : Mr.J.Chandrasekaran For Respondents : Mr.P.T.Ramkumar http://www.judis.nic.in
PUSHPA SATHYANARAYANA, J.
rsi
O R D E R
When the matter is taken up for hearing, the learned counsel appearing for the petitioner seeks permission of this Court to withdraw this petition. He has also made an endorsement in the petition to that effect.
2. In view of the submission and endorsement made by the learned counsel for the petitioner, the Original Petition is dismissed as withdrawn. No costs.
02.07.2019 rsi O.P.No.314 of 2019 http://www.judis.nic.in