Madras High CourtCMP/8859/2024allowed
Gorantla Geosynthetics Private Limited v. M/S.Akshaya Signature Homes Private Limited
2024-07-04Honourable Mr Justice R. Subramanian,Honourable Mr.Justice R.Sakthivel1 pages
C.M.P.No.8859 of 2024 in C.M.S.A.Sr.No.36726 of 2024 R.SUBRAMANIAN, J.
and R.SAKTHIVEL, J.
Though the learned counsel for the 2nd and 3rd respondents would have very serious objection for condonation of delay, considering the reasons assigned in the affidavit filed in support of the petition and the length of the delay we deem it fit to allow this petition with a view to give opportunity to the appellant to prosecute the appeal on merits.
2. Hence, this petition is ordered and the delay of 38 days in filing the above appeal is condoned.
(R.S.M., J.) (R.S.V., J.) 04.07.2024 dsa https://www.mhc.tn.gov.in/judis 1/1