R.Kumar v. The Bank Of Baroda
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 01-08-2025
CORAM
THE HONOURABLE MR JUSTICE N. SATHISH KUMAR and CMP No.10134 of 2019
1. R.Kumar 2.S.Gomathi Petitioners in both CRPs Vs
1. The Bank of Baroda Rep By Its Branch Manager, Nambiyur Branch, Nambiyur Town, Gobichettipalayam Tk, Erode District 2.Jayalakshmi Textiles Rep By Its Proprietor Bhuvaneswaran, Chinnagoundanur, Polavapalayam Village, Gobichettipalayam Tk, Erode District 3.K.K. Bhuvaneswaran 4.K.Selvaraj 5.Muthayammal 1/7
6.G.V. Kalidas 7.G.M. Venkateswaran Respondents in both CRPs PRAYER in CRP No.1530 of 2019:
This Civil Revision Petition under Article 227 of the Constitution of India has been filed to set aside the ex-parte decree and judgement dated 30-08-2017 passed in EA.No.86/2017 in EP.No.203/2006 in OS.275/1999 and allow the CRP.
PRAYER in CRP No.1531 of 2019:
This Civil Revision Petition under Article 227 of the Constitution of India has been filed to set aside the ex-parte decree and judgement dated 30-08-2017 passed in EA.No.87/2017 in EP.No.203/2006 in OS.275/1999 and allow the CRP.
For Petitioners:
in both CRPs M/s. K. Soundararajan For Respondents:
in both CRPs R1 & R5- None appeared R2 to R4 and R6 &R7 dismissed vide order dated 08.02.2023 2/7
COMMON ORDER Challenge has been made seeking direction to the Trial Court to number the application filed to restore the applications in E.A.Nos.86 & 87 of 2017, which were dismissed for default on 30.08.2017.
2. Originally, a suit in O.S.No.275 of 1999 on the file of the Principal Subordinate Court, Gobichettipalayam, had been filed by the first respondent/plaintiff against the respondents 2 to 7/defendants, and judgment was passed in the said suit on 29.03.2001.
3. Subsequently, the first respondent had also filed E.P.No.203 of 2006, in which, Attachment notice was ordered, and auction notice was also issued on 27.12.2018, stating that the auction would be conducted on 07.02.2019. Hence, the petitioners herein filed an application in E.A.No.86/2017 under Order 21 Rule 58 of CPC to cancel the Attachment order dated 18.01.2012 and claimed right over the first item of the suit schedule mentioned property. They also filed another application in E.A.No.87 of 2017 under Order 21 Rule 59 of CPC to 3/7
stay all further proceedings in E.P.N.203 of 2006 till disposal of the E.A.No.86 of 2017. Both E.A.Nos.86 & 87 of 2017 were dismissed by the Execution Court as the petitioners had not turned up to begin the enquiry. To restore both E.As, the revision petitioners filed applications before the E.P. Court. So far, both the petitions have not been numbered, hence, the petitioners are before this Court with this revision.
4. According to the petitioners, the first petitioner has purchased the property on 22.01.2008, whereas, the attachment has been effected by the Execution Court in the year 2012 and the auction was later scheduled to be conducted on 07.02.2019. In this regard, he filed an application to adjudicate his right in the first item of the suit schedule property. That application was originally numbered as E.A.No.86 of 2017. Besides, he had also filed a stay application in E.A.No.87 of 2017 to stay the execution proceedings. Both applications were dismissed for default on 30.08.2017. Though the petitioners filed applications to restore the said E.A.Nos.86 & 87 of 2017 within the stipulated time, i.e. on 22.09.2017, the said applications have not been 4/7
numbered so far.
5. This Civil Revision Petition stands dismissed as against the respondents 2 to 4, 6 and 7, for non compliance with the requirements of the Registry including payment of batta vide order dated 08.02.2023.
6. Though Mr.Revathi Manivannan, learned counsel takes notice for the respondents 1 and 5, he neither filed vakalat nor appeared on behalf of them.
7. I have considered the submissions made by the learned counsel for the petitioners and perused the materials available on records carefully.
8. It is seen from the records that such applications have been filed on 22.09.2017 itself within the period of limitation, which were returned. Again, the same were re-presented on many dates, however, they were not yet numbered. Hence, this court is inclined to allow the Civil Revision Petitions. 5/7
9. Accordingly, these Civil Revision Petitions are allowed and the Execution Court is directed to number the applications filed for restoration of E.A.Nos.86 & 87 of 2017 and dispose of the same on its own merits and in accordance with law, within a period of two (2) months from the date of receipt of a copy of this order. Consequently, connected miscellaneous petition is closed. No costs.
01-08-2025 mrp Index:Yes/No Speaking/Non-speaking order Internet:Yes To 1.The Principal Sub Court, Gobichettipalayam.
2. The Bank of Baroda Rep By Its Branch Manager, Nambiyur Branch, Nambiyur Town, Gobichettipalayam Tk, Erode District.
6/7
N.SATHISH KUMAR J.