K.S.Sumathi v. The Union Of India
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 02.04.2025
CORAM
THE HONOURABLE MR.JUSTICE N.ANAND VENKATESH and W.M.P.Nos.9624, 9625 & 12979 of 2025
1. K.S.Sumathi Wife of Vinoth Selvakumar, No.16/19, Ramasamy Nagar, Kavundampalayam, Coimbatore 641 030.
2.K.Shanmugasundaram Son of Kandasamy, No.5 Srimathi Illam, Balaji Layout, Velan Nagar, Coimbatore North - 641 006.
3.K.Easwaran Son of Kandasamy, D.No.114/177B, Iswarya Avenue, Bharathiyar Road, Maniakarampalayam, Coimbatore North - 641 006.
4.K.K.Jayakumar Son of Kumarasamy, No.26 C.K.Colony, New Siddhapudhur, Coimbatore - 641 044.
Petitioners Vs 1/6
1. The Union of India Represented By its Secretary To Government, Ministry of Petroleum and Natural Gas, Shastri Bhawan, New Delhi 110001.
2.Petroleum And Natural Gas Regulatory Board (PNGRB) Represented By its Chairperson, 1st Floor, World Trade Center, Babar Road, Barakhamba, New Delhi 110001.
3.The District Collector, Office of The District Collector, Tiruppur District, Tiruppur.
4.The Project Manager Irugur-Devangonthi Pipeline Project - Project Office, Bharat Petroleum Corporation Limited, Irugur, Coimbatore.
5.The Authroised Officer / Competent Authority, Irugur-Devangonthi Pipeline Project, Bharat Petroleum Corporation Limited, No.5, Plot No.1 & 2, Mahalakshmi Avenue, Palladam, Tiruppur District 614 664.
Respondents Writ Petition filed under Article 226 of the Constitution of India seeking issuance of a Writ of Certiorari calling for the records of the impugned paper publication of the 5th respondent issued in the Tamil Daily Newspaper "Daily Thanthi (Dhina Thanthi)", Tiruppur Edition dated 24.11.2024 under Section 7(1) of the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962 and quash the same.
2/6
For Petitioner : Ms.A.Pramila For Respondents : Mr.T.M.Pappiah [R1] Mr.P.Sathish Additional Government Pleader [R3] Mr.Krishna Srinivasan for M/s.S.Ramasubramaniam Associates[R4] Mr.AR.L.Sundaresan, Additional Solicitor General-I for Mr.O.S.Karthikeyan [R5] *****
O R D E R
This writ petition has been filed challenging the impugned publication of the fifth respondent made in Daily Thanthi, Tiruppur Edition dated 24.11.2024 under Section 7(1) of the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962.
2. Heard Ms.A.Pramila, learned counsel for petitioner, Mr.T.M.Pappiah, learned counsel appearing for first respondent, Mr.P.Sathish, learned Additional Government Pleader appearing for third respondent, Mr.Krishna Srinivasan, learned Senior Counsel appearing for fourth respondent and Mr.AR.L.Sundaresan, learned Additional Solicitor General-I appearing for fifth respondent.
3/6
3. In the considered view of this Court, it is not necessary for this Court to go into the merits of this case since the issue in hand is squarely covered by two earlier orders passed by this Court in W.P.No.38435 of 2024 etc. batch dated 21.12.2024 and W.P.No.37936 of 2024 etc. batch dated 29.01.2025. The grounds that have been raised in the present writ petition were considered by two learned Judges of this Court and it was rejected and those writ petitions were dismissed. I am in complete agreement with the reasoning that has been assigned in these two orders and hence, the present writ petition must also suffer the same fate.
Accordingly, this writ petition is dismissed. No costs. Consequently, connected miscellaneous petitions are closed. 02.04.2025 Index: Yes/no Speaking Order/Non-Speaking Order gm 4/6
To
1. The Secretary To Government, Union of India Ministry of Petroleum and Natural Gas, Shastri Bhawan, New Delhi 110001.
2.The Chairperson, Petroleum And Natural Gas Regulatory Board (PNGRB) 1st Floor, World Trade Center, Babar Road, Barakhamba, New Delhi 110001.
3.The District Collector, Office of The District Collector, Tiruppur District, Tiruppur.
4.The Project Manager Irugur-Devangonthi Pipeline Project - Project Office, Bharat Petroleum Corporation Limited, Irugur, Coimbatore. 5.The Authroised Officer / Competent Authority, Irugur-Devangonthi Pipeline Project, Bharat Petroleum Corporation Limited, No.5, Plot No.1 & 2, Mahalakshmi Avenue, Palladam, Tiruppur District 614 664.
5/6
N.ANAND VENKATESH, J gm 02.04.2025 6/6