IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED : 21.03.2025

CORAM

THE HONOURABLE Mr. JUSTICE N. ANAND VENKATESH P.C.Sekar .... Petitioner Vs 1.The Sub Collector / Revenue Divisional Officer Mettur Revenue Division Mettur Dam-1 Salem District.

2.The Tahsildhar Mettur Taluk Mettur Dam-1 Salem District.

.... Respondents Prayer : Writ Petition filed under Article 226 of Constitution of India praying to issue a Writ of Mandamus directing the first respondent to conduct an enquiry based on the application of the petitioner dated 21.10.2024 for rectifying corrections in the FMB of S.No.72/1E1A2A1A1A and consequently issue separate patta in respect of his property in S.No.72/1E1A2 to an extent of 4,570 sq.ft. situated at Thethigiripatti Village, Mettur Taluk, Salem District. 1/4

For Petitioner : Mr.M.R.Jothimanian For Respondents : Mr.A.Selvendran Special Government Pleader

ORDER

This writ petition has been filed for issue of Writ of Mandamus directing the first respondent to conduct enquiry based on the application submitted by the petitioner on 21.10.2024, wherein the petitioner is seeking for the rectification of FMB sketch and consequently to issue separate patta in the name of the petitioner.

2. When the matter is taken up for hearing today, the learned Additional Government Pleader appearing on behalf of the respondents produced the written instructions received from the first respondent. It is seen the first respondent has fixed the enquiry on 08.04.2025 at 11.00 a.m., The learned Additional Government Pleader submitted that the petitioner will be heard and thereafter necessary orders will be passed within the time frame fixed by this Court.

2/4

3. Taking into consideration the facts and circumstances of the case and the materials placed before the Court, and taking note of the written instructions received from the first respondent, there shall be a direction to the first respondent to consider and pass orders on merits and in accordance with law, within a period of eight weeks from 08.04.2025.

4. This writ petition is disposed of with the above directions. No costs. 21.03.2025 Index : Yes/No Speaking Order/Non-Speaking Order ds To:

1.The Sub Collector / Revenue Divisional Officer Mettur Revenue Division Mettur Dam-1 Salem District.

2.The Tahsildhar Mettur Taluk Mettur Dam-1 Salem District.

3/4

N. ANAND VENKATESH., J ds 21.03.2025 4/4