IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED : 10.12.2021

CORAM:

THE HONOURABLE MR.JUSTICE M.S.RAMESH W.P.No.11858 of 2018 Workmen of Lanson Motors Pvt. Ltd Through United Labour Federation Regn.No.2657/CNI Rep by its Secretary, No.149, IV Floor, C.J.Complex, Thambu chetty street, Chennai 600 001.

...Petitioner

-Vs1. The Government of Puducherry, Rep by its Secretary, Department of Labour and Employment, Beach Road, White Town, Puducherry 605 001.

2. The Labour Officer (Conciliation), No.15, First Floor, Nehur Nagar, Puducherry.

3. The Management of Lanson Motors Pvt. Ltd., Rep by its Managing Director, No.53/1A, Cuddalore Main Road, Opp Rajiv Gandhi Engineering College, Bahoor, Kirumapakkam, Puducherry 607 402.

...Respondents

PRAYER: Writ Petition filed under Article 226 of the Constitution of India, praying to issue a Writ of Mandamus to direct the 2nd respondent to forward the Conciliation Failure Report to the 1st respondent Government and further direct the 1st respondent Government to pass orders with regard to the reference of the Industrial Dispute covered by the Conciliation Ref.No.325/LO(C)/AIL/2017 under Section 10(1) of the Industrial Disputes Act, 1947 expeditiously and within such time as stipulated by this Court.

For Petitioner : Mr.P.Ganeshram For Respondents: Mr.G.Djearany, Government Advocate for R1 & R2 Mr.M.S.Soundara Rajan for R3 https://hcservices.ecourts.gov.in/hcservices/

O R D E R

The petitioner agreed inaction on the part of the Government in not making a reference of the Conciliation Failure Report dated 05.07.2018.

2.The learned Government Advocate had produced a Government Order in G.O.Rt.No.131/AIL/LAB/T/2018, Labour Department, dated 05.09.2018 and that reference was made with regard to issues. The learned Government Advocate submitted that these references were taken on file before the Labour Court in an Industrial Disputes Act and the same is pending.

3.As such, the prayer sought for in the Writ Petition has become infructuous. Accordingly, this Writ Petition is dismissed as infructuous. No costs.

Sd/- Assistant Registrar(CS-VI) //True Copy// Sub Assistant Registrar vkr To:

1. The Secretary, Government of Puducherry, Department of Labour and Employment, Beach Road, White Town, Puducherry 605 001.

2. The Labour Officer (Conciliation), No.15, First Floor, Nehru Nagar, Puducherry.

3. The Managing Director, Management of Lanson Motors Pvt. Ltd., No.53/1A, Cuddalore Main Road, Opp Rajiv Gandhi Engineering College, Bahoor, Kirumapakkam, Puducherry 607 402.

W.P.No.11858 of 2018 GSM(CO) RGA(21/12/2021) https://hcservices.ecourts.gov.in/hcservices/