← Library
Madras High CourtWP/11529/2021dismissed as infructuous

P.Rayin v. The Commissioner Of Municipal Administration

2025-03-13Honourable Mr Justice J.Sathya Narayana Prasad5 pages

IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED: 13-03-2025

CORAM

THE HONOURABLE MR JUSTICE J.SATHYA NARAYANA PRASAD P.Rayin Government Contractor, Chungam, Cherambadi, Nilgiris-643 205 Petitioner(s) in W.P.No.11529 of 2020 P.Rayin Constructions Company Pvt. Ltd., Rep. By its Director, Cherambadi, The Nilgiris 643 205.

Petitioner in W.P.No.11545 of 2020 Vs

1. The Commissioner of Municipal Administration, Ezhilagam, Chepauk, Chennai 600 005.

2.The Regional Director Head of Municipal Administration, Kumaran Shopping Complex, Near Tirupur Railway Station, Kumaran Road, Tiruppur -641 601 3.The Commissioner,

Nelliyalam Muncipalitiy, Pandalur, The Nilgiris.

Respondent(s) in both W.P's PRAYER in WP No. 11529 of 2021:

This Writ Petition filed under Article 226 of the Constitution of India for issuance of a Writ of Certiorarified Mandamus, calling for the records of the Third Respondent relating to the impugned order Na.Ka.No.2345 / 2020 / E1 dated 22.12.2020 and consequentially direct the Third respondent to quash the said order dated 22.12.2020 and consequentially direct the Third Respondent to make payment of the said outstanding sum of Rs.32,56,753/- (Thirty Two Lakhs fifty Six Thousand Seven Hundred and Fifty Three only) with interest at the rate of 24 % per annum for the period of from the date of due till the date of actual payment, within a time frame as may be fixed by this Court.

PRAYER in WP No. 11545 of 2021:

This Writ Petition filed under Article 226 of the Constitution of India for issuance of a Writ of Certiorarified Mandamus, calling for the records of the Third Respondent relating to the impugned order Na.Ka.No.2344/2020 / E1 dated 22.12.2020 and quash the said order dated 22.12.2020 and consequentially directing the Third respondent to make payment of the said outstanding sum of Rs.2,82,83,942/-(Rupees Two Crores Eighty Two lakhs Eighty Three Thousand Nine Hundred Forty Two only ) with interest at the rate of 24 % per annum for the period from the date of due till the date of actual payment, within time frame as may be fixed by this Court.

Appearance of counsel in both W.P's For Petitioner(s):

Mr.P.Anbarasan For Respondent(s):

Mr.M.S.Pream Kumar Government Advocate for R1 & R2 M/s.P. Srinivas, For R3 COMMON ORDER Today, when these matters are taken up for hearing, the learned counsel appearing for the petitioner submitted that these petitions have been filed claiming the payments for the works done by the petitioner under the Work Orders of the respondents herein. He would further submit that the payments have been settled for the works done by the petitioner.

2. In view of the above submissions made by the learned counsel for the petitioner, nothing survives for further adjudication. Accordingly, these Writ Petitions are dismissed as infructuous. No Costs. 13-03-2025 Index:Yes/No Speaking/Non-speaking order Internet:Yes

jd To 1.The Commissioner of Municipal Administration Ezhilagam, Chepauk, Chennai-600005 2.The Regional Director Head of Municipal Administration Kumaran Shopping Complex, Near Tirupur Railway Station, Kumaran Road, Tiruppur -641 601 3.The Commissioner Nelliyalam Muncipalitiy, Pandalur, The Nilgiris.

J.SATHYA NARAYANA PRASAD J.

jd WP Nos. 11529 & 11545 of 2021 13-03-2025