IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED: 15.04.2021 CORAM :

THE HON'BLE MR.SANJIB BANERJEE, CHIEF JUSTICE AND THE HON'BLE MR.JUSTICE SENTHILKUMAR RAMAMOORTHY W.P.No.18769 of 2019 Anandhan .. Petitioner Vs.

1.The Director, Tamil Nadu Slum Clearance Board, 5, Kamarajar Salai, Chennai.

2.The Deputy Commissioner, Greater Chennai Corporation, Manali Zone II, Chennai.

3.The Director, Tamilnadu Electricity Board (TANGEDCO), Anna Salai, Chennai.

4.The Director, Chennai Metro Water Supply and Sewage Board, Chindaripet, Chennai.

5.The Executive Engineer, Tamil Nadu Slum Clearance Board, Tondiarpet, Chennai.

.. Respondents Petition filed under Article 226 of the Constitution of India praying for issue of Writ of Mandamus directing the respondents to dispose of the petitioner's representation dated 5th respondent on 20.02.2019 and 1 to 4 respondents on 06.03.2019.

For Petitioner : Mr.M.J.Nissar Ahmed For Respondents : Mr.M.Rajasekar for respondent Nos.1 and 5

: Mr.R.Gopinath for respondent No.2

ORDER

(Order of the Court was made by Senthilkumar Ramamoorthy, J.) The writ petitioner complains about the alleged encroachment in Plot Nos.192 to 213 at M.G.R. Nagar, Manali Scheme.

2. The writ petitioner asserts that the aforesaid Plots belong to the Tamil Nadu Slum Clearance Board, but have been illegally occupied by various private parties, who have also put up construction thereon. In spite of issuing representations to the official respondents, it is stated that no action has been taken thereon.

3. Learned Standing Counsel for the Tamil Nadu Slum Clearance Board relies upon the status report dated March 12, 2021, wherein at paragraph 5, the details of occupants of Plot Nos.192 to 213 of M.G.R. Nagar, Manali Scheme have been tabulated. As per the said table, except for the occupant of Plot No.201, who is an allottee, all other occupants appear to be encroachers. Accordingly, it is represented that appropriate action would be taken to evict such illegal occupants in accordance with the Tamil Nadu Slum Clearance Board Act.

4. In view of the aforesaid submissions, W.P.No.18769 of 2019 is disposed of by directing the Executive Engineer, Tamil Nadu Slum Clearance Board, Tondiarpet, Chennai to initiate and conclude such eviction proceedings in accordance with law within a period of three months from the date of receipt of a copy of this order. There will be no order as to costs. Sd/- Assistant Registrar(CS III) //True Copy// Sub Assistant Registrar bbr

To:

1.The Director, Tamil Nadu Slum Clearance Board, 5, Kamarajar Salai, Chennai.

2.The Deputy Commissioner, Greater Chennai Corporation, Manali Zone II, Chennai.

3.The Director, Tamilnadu Electricity Board (TANGEDCO), Anna Salai, Chennai.

4.The Director, Chennai Metro Water Supply and Sewage Board, Chindaripet, Chennai.

5.The Executive Engineer, Tamil Nadu Slum Clearance Board, Tondiarpet, Chennai.

+2 cc to Mr.M.J.Nissar Ahmed, Advocate SR No.23339 +1 cc to Mr.R.Gopinath,Advocate SR No.22843 +1 cc to Mr. Raja SeKhar, Advocate Sr No.22737 W.P.No.18769 of 2019 15.04.2021 GPL(CO) RG.28.04.2021(3P/10C)