M/S.Shilpi Engineering Pvt.Ltd., v. Chennai Petroleum Corporation Limited,
A. No.1438 of 2025 M/s.Shilpi Engineering Pvt. Ltd.
... Applicant Vs.
M/s. Chennai Petroleum Corporation Ltd.
... Respondent ABDUL QUDDHOSE.J., This application has been filed under Section 29A of the Arbitration and Conciliation Act, seeking extension of time for the arbitrator to pronounce the arbitral award by a period of six months i.e., from 04.02.2025 to 03.08.2025.
2. Learned counsel appearing for the respondent has stated no objection for allowing this application.
3. This Court is also satisfied with the reasons stated in the affidavit filed in support of this application since sufficient cause has been shown. Accordingly, this application is allowed as prayed for by extending the time for the arbitrator to pronounce the arbitral award by a period of six months from 04.02.2025 to 03.08.2025.
20.03.2025 ab 1/2 https://www.mhc.tn.gov.in/judis
ABDUL QUDDHOSE.J., ab A. No.1438 of 2025 20.03.2025 2/2 https://www.mhc.tn.gov.in/judis