← Library
Madras High CourtCONT P/1618/2025closed

Minor.K.Lokeshwaran v. R.A.Prabhakaran

2025-07-16Honourable Mr Justice G.K. Ilanthiraiyan4 pages

IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED : 16.07.2025

CORAM

THE HONOURABLE Mr. JUSTICE G.K.ILANTHIRAIYAN Minor K. Lokeshwaran Rep. by his mother and Natural Guardian K.Sulochana ... Petitioner Vs.

R.A.Prabhakaran Executive Engineer, Zone-7, Ward no.79, Ambattur Corporation, Ambattur, Chennai - 600 053.

... Respondent Prayer:- Contempt petition has been filed under Section 11 of the Contempt of Courts Act, 1971, praying to punish the respondent herein for his willful and deliberate acts of disobedience and defiance of the order of this Court dated 12.08.2024 in W.P.No.13048 of 2024 under Section 12 of the Contempt of Court Act, 1971.

For Petitioner : Mr.Shabeer Ali H For Respondent : Mr.D.B.R.Prabhu Standing Counsel

ORDER

This Contempt Petition has been filed to punish the respondent for non compliance of the order dated 12.08.2024, passed by this Court in W.P.No.13048 of 2024, thereby directed the respondent to obtain a stability certificate and accordingly act on the representation submitted by the petitioner, within a period of four weeks.

2.

The learned Standing Counsel appearing for the respondent submitted that as directed by this Court, the respondent obtained stability certificate given by the Class-1A Engineer that the building is structurally sound to be used as a public building. He also produced the copy of the Stability report and other communications along with the status report filed by the respondent.

3.

Recording the said submission, this Contempt Petition is closed. 16.07.2025 Index : Yes/No : Yes/No Speaking/Non Speaking order rts

To The Executive Engineer, Zone-7, Ward no.79, Ambattur Corporation, Ambattur, Chennai - 600 053.

G.K.ILANTHIRAIYAN, J.

rts 16.07.2025