IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED : 03.09.2018

CORAM

THE HONOURABLE MR. JUSTICE R.MAHADEVAN W.P.No. 22509 of 2018 V.Govindarasu .. Petitioner Vs

1. The District Collector, Office of the District Collector, Thiruvarur District.

2.The Block Development Officer, Muthupettai Panchayath Union, Thiruvarur District.

3.The Assistant Executive Engineer (RD), Thiruthuraipoondi, Thiruvarur District. .. Respondents Writ Petition filed under Article 226 of the Constitution of India, praying to issue a writ of Mandamus, directing the respondents to consider the petitioner's representation dated 20.07.2018 to disburse the amount of Rs.9 lakhs for the contract work done by the petitioner in the work order in Na.Ka.2918/A4/2012 dated 25.02.2014.

For Petitioner : Mr.Greetha Senthikumar For Respondents : Mr.V.Jayaprakash Narayanan, Special Government Pleader

ORDER

By consent of both parties, the writ petition is taken up for final disposal at the admission stage itself.

2.The petitioner has come up with this writ petition seeking a direction to the respondents to consider his representation dated 20.07.2018 to disburse the amount of Rs.9 lakhs for the contract work done by him in the work order in Na.Ka.2918/A4/2012 dated 25.02.2014. 3.According to the learned counsel for the petitioner, the petitioner has submitted a representation dated 20.07.2018, but, the same is yet to be disposed of by the respondents. Hence, the petitioner is before this Court.

4.Mr.V.Jayaprakash Narayanan, learned Special Government Pleader taking notice for the respondents, submitted that the respondents be directed to consider the petitioner's representation and pass orders in accordance with law.

5.Considering the facts and circumstances of the case and having regard to the submissions made by

the learned counsel on either side, this Court directs the respondents to consider the petitioner's representation dated 20.07.2018 on the basis of the completion certificate issued by the competent authority and pass appropriate orders, on merits and in accordance with law, after affording due opportunity of hearing to the petitioner as well as any of the interested parties, within a period of six weeks from the date of receipt of a copy of this order. 6.Accordingly, this writ petition stands disposed of. No costs. 03.09.2018 Index: Yes/No vga R.MAHADEVAN, J.

vga To

1. The District Collector, Office of the District Collector, Thiruvarur District.

2.The Block Development Officer, Muthupettai Panchayath Union, Thiruvarur District.

3.The Assistant Executive Engineer (RD), Thiruthuraipoondi, Thiruvarur District.

W.P.No. 22509 of 2018 03.09.2018