Sunil Hi Tech Engineers Ltd (Under Liquidaion) v. Bgr Energy Systems Pvt Ltd
A.No.2882 of 2022 in Arb.O.P.(Com.Div.)No.186 of 2022 A.No.2882 of 2022 in Arb.O.P.(Com.Div.)No.186 of 2022 M.SUNDAR, J., Read this in conjunction with and in continuation of earlier proceedings made in the captioned main 'Arbitration Original Petition' [hereinafter 'Arb.OP' for the sake of brevity] in the previous listings.
2. Suffice to say that the captioned application has been taken out with a prayer to amend the main Arb OP as an inadvertent typographical / secretarial error has crept in qua name of Hon'ble Arbitrator whose mandate is sought to be terminated.
3. Mr.Avinash Wadhwani, learned counsel adverting to support affidavit submits that inadvertent error came to light only when the matter was listed for hearing. This is articulated in paragraph No.3.
4. In the light of innocuous but imperative nature of prayer, captioned application is ordered as prayed for . https://www.mhc.tn.gov.in/judis Page Nos.1/2
A.No.2882 of 2022 in Arb.O.P.(Com.Div.)No.186 of 2022 M.SUNDAR, J., mk
5. Learned counsel for the applicant / petitioner to carry out necessary and consequential amendments within one week from today i.e., on or before 02.08.2022. Learned counsel to file amended copy of Arb OP within one week there from i.e., before 09.08.2022.
6. List the captioned Arb OP on 10.08.2022.
26.07.2022 mk A.No.2882 of 2022 in Arb.O.P.(Com.Div.)No.186 of 2022 https://www.mhc.tn.gov.in/judis Page Nos.2/2