O.A.No.293 to 295 of 2024 O.A.No.293 to 295 of 2024 KRISHNAN RAMASAMY, J.

In the present case, vide order dated 12.04.2024, this Court had granted an order of interim injunction.

2. Subsequent to the said order, both the parties appointed the Arbitrators of their choice and now, only the presiding Arbitrator has to be appointed. Hence, both the learned counsel requested this Court to pass appropriate orders.

3. Therefore, considering the above submissions, this Court is inclined to extend the interim injunction already granted by this Court.

4. Accordingly, the interim order already granted by this Court, vide order dated 12.04.2024, is extended till the date of first hearing before the Arbitral Tribunal.

Page No.1/2 https://www.mhc.tn.gov.in/judis

O.A.No.293 to 295 of 2024 KRISHNAN RAMASAMY, J.

nsa

5. In the meantime, the parties are directed to initiate the arbitration proceedings to adjudicate the dispute between them, where, these applications shall be considered as Section 17 applications and accordingly, the respective parties may make submission for further continuation of the interim injunction granted by this Court.

6. In the result, these original applications stand disposed of. No cost.

10.06.2024 nsa O.A.No.293 to 295 of 2024 Page No.2/2 https://www.mhc.tn.gov.in/judis