IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED : 29.06.2017 CORAM :

THE HONOURABLE MR. JUSTICE M.M.SUNDRESH WRIT PETITION No. 14905 of 2017 & W.M.P.Nos.16146 & 16147 of 2017 M/s.Current Power Equipments Private Limited, Represented by its Director Mr.M.Saravanan, Survey No.184/2&213, Thirumudivakkam Village, (NEAR SIDCO), Sriperumbudur, Kanchipuram District, Chennai - 600 044.

... Petitioner Vs.

1. The Chairman, Tamil Nadu Electricity Board, No.144, Annal Salai, Chennai - 02.

2. The Chief Engineer, Material Management, TANGEDCO, No.144, Annal Salai, Chennai - 02.

3. M/s.Supreme Power Equipment Private Limited, Rep by its Managing Director Mr.Vee.Rajmohan, No.55, Sidco Industrial Estate, Thirumazhisai, Chennai - 600 124.

4. S.L.Electricals, Rep by its Prop. T.Srinivasan, No.325, Odaman Nagar, Vannagaram, Chennai - 95.

5. SAP Industries, Rep by its CEO, R.Harirajan, Plot No.51, Industrial Estate, Thirumudivakkam, Chennai - 44.

6. Sarayu Engineering, Rep by its CEO, R.Venkateswaran, No.35, Padiyur Road, Kulathur, Dindugal - 5.

7. Venkateswara Electrical Industries Private Limited, Rep by its Managing Director, A.Sivasubramani, No.74, Kundrathur Road, Porur, Chennai - 76.

8. Bala Industries, Rep by its Managing Partner, S.A.Arulselvam, No.53, Multi Industrial Nagar, Gerugambakkam, Chennai - 128.

9. Hindustan Transformers, Rep by its Managing Partner, V.Ramesh, No.37-B, Sidco Industrial Estate, Thirumazhisai, Chennai - 124.

10.EMMESS Control Private Limited, Rep by its Managing Director Mr.Srinivasan, D.P. 90,91 & 92, SIDCO Industrial Estate, Thirumazhisai, Chennai - 124.

11.Sri Venkateswara Engineering Works, Rep by its Proprietor Mr.P.Babu, No.160, Sangaralingam Street, Gerugambakkam, Chennai - 128.

12.M/s.EVR Electricals Private Limited, Rep by its Director Mr.Elumalai, No.64, Ponni Amman Nagar, Ayanambakkam, Chennai - 600 095.

... Respondents (R3 to R12-Impleaded as per Order dated 20.06.2017 in WMP. Nos.16777,16778, 16788 to 16793/2017 in W.P. Nos.14905/2017) Prayer : Petition filed under Article 226 of the Constitution of India, to issue a Writ of Mandamus directing the respondents to open Envelope-B (Price Bid) of the petitioner submitted for supply of energy efficiency transformers in response to Specifications Numbers M-16/16-17, M-19/16-17 & M-23/16-17 dated 20.01.2017 to 07.02.2017 and to place purchase orders for supply of transformer.

For Petitioner : Mr.P.S.Raman Senior Counsel for M/s.R.Sivaraman For Respondents:Mr.Yashod Vardan Senior Counsel For Mr.S.K.Rameshwar (For R1 & R2) Mr.P.Solomon Frances (For R3 to R12)

O R D E R

This writ petition has been filed by the unsuccessful tenderer seeking a direction to the respondents to open its price bid.

2.On facts, there is no dispute that the petitioner was unable to comply with the time extended by this Court which has become final by the orders of the Apex Court. It is also not in dispute that the time was extended with a rider that no more extension would be granted. Now the petitioner's case falls beyond the time granted by this Court.

3.In such view of the matter, this Court does not find any merit in this writ petition. Accordingly, this writ petition stands dismissed. No costs. Consequently, connected miscellaneous petitions are closed.

Sd/- Asst.Registrar (CO) /true copy/ Sub Asst. Registrar To

1. The Chairman, Tamil Nadu Electricity Board, No.144, Annal Salai, Chennai - 02.

2. The Chief Engineer, Material Management, TANGEDCO, No.144, Annal Salai, Chennai - 02.

+1cc to Mr.P.Soloomon Francis,Advocate sr.45175 W.P.No.14905 of 2017 & W.M.P.Nos.16146 & 16147 of 2017 ak(co) ss(13/7/2017)