Madras High CourtWP/11516/2020disposed of

A.Nagaraj v. The Assistant Engineer

2020-09-07Honourable Mr Justice N. Anand Venkatesh3 pages

IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED: 07.09.2020

CORAM:

THE HONOURABLE MR.JUSTICE N.ANAND VENKATESH W.P.No.11516 of 2020 A.Nagaraj s/o.Arumugam ... Petitioner Vs.

1. The Assistant Engineer, K.K.Nagar and Distributions Co. (South) Chennai 600 078.

2. The Assistant Engineer, Ashok Nagar, and Distributions Co.(South) Chennai.

... Respondents (R2 suo motu impleaded vide order dated 26.08.2020 made in W.P.No.11516 of 2020 by NAVJ) PRAYER: Writ Petition filed under Article 226 of Constitution of India, seeking Writ of Mandamus, directing the respondent to provide the service connection to Bunk shop situated at No.273B, 10th Avenue, Ashok Nagar, Chennai-600 083, under Regulation 27

(4) of the Tamil Nadu Electricity Distribution Code, 2004, within a time limit that may be stipulated by this Court. For Petitioner : M/s.B.K.Girish Neelakantan For Respondent : Mr.P.Gunaraj, Standing Counsel.

O R D E R

This writ petition has been filed for issuance of Writ of Mandamus directing the respondent to provide service connection to the Bunk shop that is run by the petitioner in the subject property.

2.The case of the petitioner is that the petitioner has been allotted a bunk shop by the Tamil Nadu Khadi and Village Industries Board and he is running the bunk shop from the year 2014 onwards. The petitioner has submitted necessary documents to prove that he is running the bunk shop in the concerned place after getting the authorization of the Tamil Nadu Khadi and Village Industries Board.

The petitioner made a representation to the respondents seeking for electricity connection and the petitioner also submitted the indemnity bond and also the relevant certificates from the Ministry of Micro, Small and Medium Enterprises. The grievance of the petitioner is that the representation has not been considered. 3.Heard Mr.B.K.Girish Neelakantan, learned counsel appearing on behalf of the petitioner and Mr.P.Gunaraj, learned standing counsel appearing on behalf of the respondents. 4.Taking into consideration the facts and circumstances of the case and the limited relief sought for in the writ petition, there shall be a direction to the second respondent to consider the application submitted by the petitioner seeking for electricity connection.

The second respondent shall ensure that the petitioner is running the business after getting proper licence from the concerned authority. On such satisfaction, the second respondent shall consider granting service connection to the petitioner under Tamil Nadu Electricity Distribution Code, 2004, after getting necessary indemnity bond from the petitioner. This process shall be completed within a period of four weeks from the date of receipt of copy of this order. 5.This writ petition is disposed of with the above directions. No costs.

s/d- Assistant Registrar True Copy Sub-Assistant Registrar rm To

1. The Assistant Engineer, K.K.Nagar and Distributions Co. (South) Chennai 600 078.

2. The Assistant Engineer, Ashok Nagar, and Distributions Co.(South) Chennai.

W.P.No.11516 of 2020 LN(CO) SP(29/09/2020)