← Library
Madras High CourtA/1832/2025allowed

M/S.Sk Engineering And Construction Company, v. M/S.Bharat Heavy Electricals Limited.,

2025-04-07Honourable Mr Justice Abdul Quddhose2 pages

A.No. 1832 of 2025

IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED: 07-04-2025

CORAM

THE HONOURABLE MR JUSTICE ABDUL QUDDHOSE A.No. 1832 of 2025 M/s.S.K. Engineering and Construction Company, Rep by its Authorised Signatory, T.Sivakumar, I Floor,Unit B-4, TNHB Flats, Fairlands, Salem-636016.

..Applicant Vs M/s.Bharat Heavy Electricals Limited., Rep by its General Manager, Power Plant Piping Unit, Thirumayam-622507.

..Respondent For Applicant : Ms.Chandini Rajkishore for Mr.R.Saravanan For Respondent : Mr.S.Shyam Kumar

O R D E R

Learned counsel for the respondent has stated no objection in allowing this application.

2. This application has been filed under Section 29A of the Arbitration and Conciliation Act seeking for extension of time for the Arbitrator to pronounce the arbitral award.

ABDUL QUDDHOSE,J.

https://www.mhc.tn.gov.in/judis

A.No. 1832 of 2025

3. This Court is satisfied with the reasons contained in the affidavit filed in support of the application as sufficient cause has been shown. Accordingly, this Application is allowed as prayed for by granting three months time for the Arbitrator to pronounce the arbitral award from the date of receipt of a copy of this order.

07.04.2025 vsi A.No. 1832 of 2025 https://www.mhc.tn.gov.in/judis