IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED : 08.07.2022

CORAM

THE HON'BLE MR. JUSTICE P.D. AUDIKESAVALU W.P. No. 34221 of 2016 and W.M.P. Nos. 29527 and 29528 of 2016 P.K.Vasudevan ... Petitioner -vs1. Tamil Nadu Generation and Distribution Corporation Ltd., Represented by its Chairman-cum-Managing Director, 144, Anna Salai, Chennai - 2.

2. The Secretary, Tamil Nadu Generation and Distribution Corporation Ltd., Represented by its Chairman-cum-Managing Director, 144, Anna Salai, Chennai - 2.

3. The Superintending Engineering P&A, North Chennai Thermal Power Station, Stage-II (2x600MW), TANGEDCO, Athipattu, Chennai - 120.

4. The Superintendent Engineering P&A, Mettur Thermal Power Station-I, TANGEDCO, Mettur Dam - 636 406, Salem District.

5. A.Mani ... Respondents Prayer:- Writ Petition filed under Article 226 of the Constitution of India, 1950, praying to issue a Writ of Certiorari, to call for the records pertaining to the order dated 23.09.2016 issued by the First Respondent, through the Second Respondent in Memorandum No. 31082/A1/A12/2016-1, quash the same.

For Petitioner : Ms. H.Nandhini for Mr. R.Krishnaswamy For Respondents: Mr. P.Subramanian (for R1 to R4)

O R D E R

Heard Ms. H.Nandhini, Learned Counsel appearing for the Petitioner and Mr. P.Subramanian, Learned Counsel for the First to Fourth Respondents and perused the materials placed on record, apart from the pleadings of the parties. 2.

The Writ Petition has been filed challenging the order of transfer of the Petitioner in Memorandum No. 31082/A1/A12/2016-1 dated 23.09.2016 by which he was transferred from the post of Deputy Chief Chemist/MTPS-2 to the post of Deputy Chief Chemist/MTPS-I.

3.

It has been brought to notice that subsequently, the Petitioner was again transferred by order in Memorandum No. 54503/A1/A12/2016-1 dated 24.11.2016 to the post of Deputy Chief Chemist/NCTPS-I and its copy has been produced. In view of the same, nothing remains for further consideration in the matter.

4.

In fine, the Writ Petition is disposed. Consequently, the connected Miscellaneous Petitions are closed. No costs. Sd/- Assistant Registrar(CO) //True Copy// Sub Assistant Registrar gd To

1. Chairman-cum-Managing Director, Tamil Nadu Generation and Distribution Corporation Ltd., 144, Anna Salai, Chennai - 2.

2. Chairman-cum-Managing Director, Tamil Nadu Generation and Distribution Corporation Ltd., The Secretary, 144, Anna Salai, Chennai - 2.

3. The Superintending Engineering P&A, North Chennai Thermal Power Station, Stage-II (2x600MW), TANGEDCO, Athipattu, Chennai - 120.

4. The Superintendent Engineering P&A, Mettur Thermal Power Station-I, TANGEDCO, Mettur Dam - 636 406, Salem District.

+1cc to Mr. P.Subramanian, Advocate, S.R.No.44566 +1cc to Mr.V.Ajoy khose, Advocate, S.R.No.45248 W.P. No. 34221 of 2016 SKM(CO) CT/18/07/2022