Il And Fs Tamilnadu Power Company Ltd v. Savithri
C.M.P.No.12483 of 2019 in A.S.(SR).No.60543 of 2019 M.DURAISWAMY, J.
and T.V.THAMILSELVI, J.
Mr.A.K.Raghavulu, learned counsel for the petitioner, on instructions, submitted that he is giving up the 5th respondent in the appeal.
2.The submission made by the learned counsel for the petitioner/appellant is recorded. Hence, the 5th respondent is given up in the petition as well as in the appeal.
3.There is a delay of 89 days in filing the appeal.
4.Mr.D.Baskar, learned counsel for the 1st respondent has no objection for condoning the delay.
5.The notices sent to the respondents 2 & 4 were duly served and their names have been printed in the cause list. However, none appeared for them. The notices sent to respondents 3 & 6 were refused by the respondents.
6.We are satisfied with the reasons stated in the affidavit filed in support of the petition. The delay is condoned. The petition is ordered.
[M.D.,J.] [T.V.T.S.,J.] 21.03.2022 va https://www.mhc.tn.gov.in/judis