IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED : 13.06.2016

CORAM:

THE HONOURABLE MR.JUSTICE B.RAJENDRAN W.P.No.19300 of 2016 and W.M.P.No.16777 of 2016 S.Velusamy S/o.C.Chellappan D.No.4/134 Maalipalayam Bodinaickenpatti Po Vellandivalasu Via Edapadi Taluk Salem District ... PETITIONER Vs.

1. The Tamil Nadu Electricity Generation and Distribution Corporation Ltd (TANGEDCO) Rep by its Chairman No.144 Anna Salai Chennai-600 002

2. The Chief Engineer (Personnel) The Tamil Nadu Electricity Generation and Distribution Corporation Ltd (TANGEDCO) No.144 Anna Salai Chennai-600 002

3. The Chief Engineer(Distribution) Erode Region Erode

4. The Superintending Engineer Mettur Electricity Distribution Circle Mettur Dam Salem District ... RESPONDENTS Prayer:

Writ petition filed under Article 226 of the Constitution of India, praying for the issuance of a Writ of Certiorarified Mandamus, to call for the records relating to the impugned proceedings issued by the 2nd respondent in Lr.No. 022664/418/G.26/G.262/2015 dated 27/05/2015 and to quash the same and consequently direct the respondents to alter the date of birth of the petitioner in Service Records as 07/02/1959 instead of 14/04/1957 as per original birth extract and other documents submitted along with the application dated 24/06/2013 and to allow the petitioner to continue in service in the post of Assessor uptill reaching the age of superannuation as per actual date of birth with consequential benefits within a time frame to be fixed by this Court.

For Petitioner : Mr.G.Sankaran For Respondents : Mr.P.R.Dhilip Kumar

O R D E R

After some elaborate arguments, the learned counsel for the petitioner submitted that he may be permitted to file by way of appeal to the Chairman for reduction of punishment.

2. In view of the submission made by the learned counsel for the petitioner, making it very clear that this Court is not interfering with the impugned proceedings of the second respondent, the petitioner is permitted to file an appeal to the Chairman, The Tamilnadu Electricity Generation and Distribution Corporation (TANGEDCO), Chennai 600 002 within a period of 15 days from the date of receipt of copy of this order. On receipt of such appeal, the Chairman is directed to consider the same and pass appropriate order in accordance with law within a period of two months thereafter.

3. The writ petition is disposed of with the above direction. No costs. Consequently, connected miscellaneous petition is closed.

Sd/- Assistant Registrar(CS V) //True Copy// Sub Assistant Registrar vaan To

1. The Chairman Tamil Nadu Electricity Generation and Distribution Corporation Ltd (TANGEDCO) No.144 Anna Salai Chennai-600 002

2. The Chief Engineer (Personnel) The Tamil Nadu Electricity Generation and Distribution Corporation Ltd (TANGEDCO) No.144 Anna Salai Chennai-600 002

3. The Chief Engineer(Distribution) Erode Region, Erode

4. The Superintending Engineer Mettur Electricity Distribution Circle Mettur Dam, Salem District.

+1cc to Mr.G.Sankaran, Advocate, S.R.No.31622 +1cc to Mr.P.R.Dhilip Kumar, Advocate, S.R.No.32319 W.P.No.19300 of 2016 and W.M.P.No.16777 of 2016 EV(CO) CA(23/06/2016)