IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED : 19.11.2021
CORAM
THE HONOURABLE Mr.JUSTICE G.K.ILANTHIRAIYAN WP.No.15030 of 2021 E.Ramanujam
...Petitioner
Vs 1.The Chief General Manager(T&RO), cum Regional Officer, National Highways Authority of India, Sri Tower, 3rd Floor, DP-34, (SP), Industrial Estate, Guindy, Chennai 600 002 2.The District Collector, Office of the District Collector, Cheyyar, Kanchipuram Road, Gandhipuram, Thaiyar Kullam, Kancheepuram District 631 501 3.Competent Authority, Namely, The Special District Revenue Officer, (Land Acquisition), Kancheepuram & Tiruvallur District, Office of the District Collector, Cheyyar, Kanchipuram Road, Gandhipuram, Thaiyar Kullam, Kancheepuram District 631 501 4.The Project Director, National Highway - 4, (Poonamallee - Walajahpet Section), 7/16, Govindarajan Street, (Near National Theatre), Tambaram West, Chengalpattu District 600 045
...Respondents
Prayer :- Writ Petition is filed under Article 226 of the Constitution of India praying to issue a Writ of Mandamus directing the first respondent herein to consider the petitioner's representation dated 13.03.2021 and to dispose of the same in the manner known to law by paying / awarding the compensation amount to the competent or appropriate person eligible to receive the same.
For Petitioner :
Mr.M.Karthikeyan For Respondents For R2 & 3 :
Mr.A.Selvendran, Special Government Pleader For R1 : Mr.Su.Srinivasan For R4 : M/s.S.R.Sumathy
ORDER
The petitioner filed this writ petition for direction directing the first respondent to consider his representation dated 13.03.2021 in respect of payment of compensation for the land which was acquired by the first respondent.
2. According to the petitioner, the petitioner is the owner of the property comprised in survey No.326/3 admeasuring 50 cents situated at No.103, Beemanthangal Village, Sriperumbudur, Kancheepuram District. However, he was not paid any compensation.
3. The learned counsel for the first respondent submitted that what are all the amounts awarded by the third respondent, already had been deposited and the entire award amount is lying with the third respondent for disbursement.
4. Considering the above submission, the petitioner is directed to submit a fresh representation before the third respondent within a period of two weeks from the date of receipt of copy of this order. On receipt of the same, the third respondent is directed to conduct enquiry and, after giving opportunity to the petitioner and on verification, pass orders for disbursement of the compensation within a period of eight weeks thereafter.
5. With the above direction, this writ petition is disposed of. No order as to costs.
Sd/- Assistant Registrar(CS-VIII) // True Copy // Sub Assistant Registrar lok
To 1.The Chief General Manager(T&RO), cum Regional Officer, National Highways Authority of India, Sri Tower, 3rd Floor, DP-34, (SP), Industrial Estate, Guindy, Chennai 600 002 2.The District Collector, Office of the District Collector, Cheyyar, Kanchipuram Road, Gandhipuram, Thaiyar Kullam, Kancheepuram District 631 501 3.The Special District Revenue Officer, (Land Acquisition), Kancheepuram & Tiruvallur District, Office of the District Collector, Cheyyar, Kanchipuram Road, Gandhipuram, Thaiyar Kullam, Kancheepuram District 631 501 4.The Project Director, National Highway - 4, (Poonamallee - Walajahpet Section), 7/16, Govindarajan Street, (Near National Theatre), Tambaram West, Chengalpattu District 600 045.
+1cc to Mr.C.Balaji, Advocate SR.No.60253 +1cc to the Government Pleader SR.No.60280 WP.No.15030 of 2021 NRL(CO) RVM(08/12/2021)