← Library
Madras High CourtCONT P/526/2025closed

P.M.Sivashanmugam (Deceased) v. Thiru. Michael Albert And Another

2026-06-12Honourable Mr.Justice T. Vinod Kumar4 pages

IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED: 12-06-2026

CORAM

THE HON'BLE MR.JUSTICE T. VINOD KUMAR P.M.Sivashanmugam (Deceased) Represented by his Wife S. Nirmala ..Petitioner(s) Vs 1.Thiru. Michael Albert The Superintending Engineer, Chennai Electricity Distribution Circle West, Tamilnadu Generation and Distribution Corporation Ltd., Anna Nagar, Chennai - 40.

2.Thiru. A. Sakthivel, The Executive Engineer, Operation and Maintenance, CEDC/West, TANGEDCO, Anna Nagar, Chennai - 40.

..Respondents Prayer: Petition filed under Sections 11 and 12 of Contempt of Courts Act, praying to punish the respondents under Sections 11 and 12 of the Contempt of Courts Act for disobeying the lawful Orders of this Hon'ble High Court, in W.P.No. 25107 of 2016 dated 27.09.2016 For Petitioner:

Mr. M. RAVI For Respondents:

Mr.Purushothaman, Standing Counsel

ORDER

When the matter is taken up for hearing today, learned Standing counsel appearing for TANGEDCO/respondents submits since the family members/legal heirs of the deceased petitioner are required to give legal heirship certificate for the respondent to make payment. Learned Standing Counsel further submits that upon the legal heirs furnishing the legal heirship certificate, the respondents are willing to make necessary payment due to the petitioner, thereby, complying the order of this Court in W.P.No.25107 of 2016 dated 27.09.2026.

2. In view of the aforesaid submission made by the learned Standing Counsel for the respondents of their willingness to disburse the amount due to the deceased petitioner to the legal heirs, upon L.R's of deceased petitioner furnishing legal heirship certificate, the respondents shall take the same on record and disburse the amount due to the deceased petitioner to his legal heirs, within a period of three weeks from the date of receipt of the legal heirship certificate.

3. With the above observation, this contempt petition is closed. 12-06-2026 Index: Yes/No Speaking/Non-speaking order

MSV To

1. Thiru. Michael Albert The Superintending Engineer, Chennai Electricity Distribution Circle West, Tamilnadu Generation and Distribution Corporation Ltd., Anna Nagar, Chennai - 40.

2. Thiru. A. Sakthivel, The Executive Engineer, Operation and Maintenance, CEDC/West, TANGEDCO, Anna Nagar, Chennai - 40.

T.VINOD KUMAR, J.

MSV 12-06-2026