M/S.Chandra Textiles v. The Chairman And Manaing Director
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 16.05.2019
CORAM
THE HONOURABLE MR.JUSTICE KRISHNAN RAMASAMY W.P.No.14520 of 2019 M/s.Chandra Textiles, H.T.Sc.No.039094350437 S.F.No.126/2, Pappampatti Main Road, Peedampalli (Po), Ondipudur Via, Coimbatore 641 016, Rep by its Partner Mr.S.Sureshchandran ... Petitioner ..Vs..
1. The Chairman and Managing Director TANGEDCO No.144, Anna Salai, Chennai-600 002.
2. The Superintending Engineer, Coimbatore Electricity Distribution Circle/Metro, TANGEDCO, TTABAD, 641 012, Coimbatore.
... Respondents Prayer:
Writ petition filed under Article 226 of the Constitution of India to issue a Writ of Mandamus directing the second respondent to permit the petitioner to pay the balance Additional Security Deposit of Rs.15,90,081/- alone in 10 monthly installments along with the regular current consumption charges for its H.T. Service Connection No.039094350437, M/s.Chandra Textiles.
For Petitioner : Mr.V.Veluchamy For Respondents : Mr.S.K.Raameshwar
O R D E R
Mr.S.K.Raameshwar, learned counsel takes notice on behalf of the respondents. By consent of both sides, this Writ Petition is taken up for final disposal at the stage of admission itself.
2.This Writ Petition has been seeking for a direction to the second respondent to permit the petitioner to pay the balance Additional Security Deposit of Rs.15,90,081/- alone in 10 monthly installments along with the regular current consumption charges for its H.T. Service Connection No.039094350437, M/s.Chandra Textiles.
3. The learned counsel for the petitioner states that due to acute financial crisis, consequent the movement of cotton yarn was not as expected, the petitioner was not in a position to pay the Additional Security Deposit at once and hence pleads before this Court to pay the Additional Security Deposit in 10 monthly installments. He would further submit that this Court in similar circumstances, this Court in W.P.No.16246 of 2016 has ordered for payment of Additional Security Deposit, in six equal monthly installments, along with current consumption charges and the petitioner herein is also ready and willing to pay the Additional Security Deposit by way of 6 monthly installments.
4. The learned counsel appearing for the respondents also agreed for the same.
5. Considering the facts and circumstances of the case and also having regard to the submissions made, this Writ Petition is disposed of directing the petitioner to pay the Additional Security Deposit of Rs.15,90,081/-, in six equal installments along with regular current consumption charges, commencing from 01.06.2019, failing which it is open to the respondents to initiate appropriate action in accordance with law. No costs. Sd/- Assistant Registrar(V.O) //True Copy// Sub Assistant Registrar arr/vkr To
1. The Chairman and Managing Director TANGEDCO No.144, Anna Salai, Chennai-600 002.
2. The Superintending Engineer, Coimbatore Electricity Distribution Circle/Metro, TANGEDCO, TTABAD, 641 012, Coimbatore.
+1cc to Mr.V.Veluchamy, Advocate, S.R.No.43895 W.P.No.14520 of 2019 BR(CO) CS/23/05/2019