IN THE HIGH COURT OF JUDICATURE AT MADRAS

( Special Original Jurisdiction ) Monday, the Twenty Fourth day of September Two Thousand Eighteen PRESENT THE HON`BLE MR JUSTICE R.MAHADEVAN WP No.23236 of 2018 and WMP No.27122 of 2018 DCW LTD., [ PETITIONER IN BOTH THE REP. BY ITS GENERAL MANAGER PETITIONS ] (LEGAL & INDIRECT TAXATION) M.THYAGA MOORTHY, ARUMUGANERI, SAHUPURAM P.O.

THOOTHUKUDI DISTRICT, TAMIL NADU - 628 229 Vs 1 STATE OF TAMIL NADU [ RESPONDENTS IN BOTH THE REP. BY ITS PRINCIPAL SECRETARY, PETITIONS ] PUBLIC WORKS (W2) DEPARTMENT, SECRETARIAT, FORT ST. GEORGE, CHENNAI - 600 009 2 THE SUPERINTENDING ENGINEER PUBLIC WORKS DEPARTMENT (WATER RESOURCE ORGANIZATION), TAMARAPARANI BASIN DIVISION, P.W.D. WATER RESOURCES ORGANIZATION, TIRUNELVELI.

Writ Petitions under article 226 of the Constitutions of India praying that in these circumstances stated therein and in the respective affidavits filed therewith the High Court will be pleased to (1)issue a Writ of Certiorari to call for the records of the first respondent in G.O. (Ms) No.92 Public Works (W2) Department, dated 13.04.2018 and the consequential letter of the second respondent viz. letter dated 09.07.2018, bearing reference L.No.T3/Royalty Charges (1/2018) and quash the same (in WP.23236/2018) and

(2) To stay the operation of G.O. (Ms) No.92 Public Works (W2) Department, dated 13.04.2018 issued by the first respondent and the consequential letter of the second respondent viz. letter dated 09.07.2018, bearing reference L.No.T3/Royalty Charges (1/2018), (in WMP.27122/2018) respectively pending WP.No.23236 of 2018.

https://hcservices.ecourts.gov.in/hcservices/

Order :These petitions coming on for orders upon perusing the petitions and the respective affidavits filed in support thereof and upon hearing the arguments of M/S.C.SEETHAPATHY, Advocate for the petitioner in both the petitions and of MR.V.JAYAPRAKASH NARAYANAN SPL.GOVT.PLEADER on behalf of the Respondents in both the petitions the court made the following order:- Post after two weeks for filing Counter.

Interim Order already granted by this Court on 07.09.2018 is to continue till then.

-sd/- 24/09/2018 / TRUE COPY / Sub-Assistant Registrar ( Statistics / C.S. ) High Court, Madras - 600 104.

TO 1 THE PRINCIPAL SECRETARY THE GOVERNMENT OF TAMILNADU, PUBLIC WORKS (W2) DEPARTMENT, SECRETARIAT, FORT ST.GEORGE, CHENNAI - 600 009 2 THE SUPERINTENDING ENGINEER PUBLIC WORKS DEPARTMENT (WATER RESOURCE ORGANIZATION), TAMARAPARANI BASIN DIVISION, P.W.D. WATER RESOURCES ORGANIZATION, TIRUNELVELI.

C.C. to M/S.C.SEETHAPATHY Advocate Order in WP.23236/2018 and WMP.27122/2018 Date :24/09/2018 From 26.2.2001 the Registry is issuing certified copies of the Interim Orders in this format VS 12.09.2018 RRI 27/09/2018 https://hcservices.ecourts.gov.in/hcservices/